7618 N CLAYBECK AVE 91505

Certificate Information: 7618 N CLAYBECK AVE 91505

Application / Permit
22016-20000-27625
Plan Check / Job No.
B22VN13851
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 13'-3" X 12'-6" ADDITION TO AND CONVERT (E) DETACHED STORAGE ROOM INTO A (N) DETACHED 31'-9" x 20'-3" IRREGULAR SHAPED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 5/22/2023
Issuing Office
Current Status
Issued on 5/22/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/20/2022 APPLICANT
Assigned to Plan Check Engineer 9/26/2022 JEROME MAGAT PALMA
Corrections Issued 9/27/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 4/19/2023 LUISANGEL VALENZUELA
Plan Check Approved 5/18/2023 ALFRED RAMIREZ
Issued 5/22/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/30/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 1/30/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 2/1/2023 COLIN LOREDO
Sewer availability Cleared 2/1/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/21/2023 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 7/24/2023 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/23/2023 Approved DAVID ANDERSON
PLUMBING-Final 10/23/2023 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 1/3/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 1/3/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/17/2024 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 1/17/2024 Corrections Issued CRAIG DAVIS
Green Building Rough 1/17/2024 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 1/17/2024 Corrections Issued CRAIG DAVIS
MERV13>=Rough 1/17/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 1/17/2024 Corrections Issued CRAIG DAVIS
Rough-Elec/Plmb/HVAC 1/17/2024 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 11/7/2024 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 11/7/2024 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 11/7/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 11/12/2024 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 10/3/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 10/3/2025 Approved DAVID ANDERSON
Green Building Rough 10/3/2025 Approved DAVID ANDERSON
HVAC-Rough 10/3/2025 Approved DAVID ANDERSON
MERV13>=Rough 10/3/2025 Approved DAVID ANDERSON
Drywall Nailing 3/20/2026 Approved DAVID ANDERSON