4216 N FARMDALE AVE 91604

Certificate Information: 4216 N FARMDALE AVE 91604

Application / Permit
22016-20000-27542
Plan Check / Job No.
B22VN13819
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). WORK PER WFPP.
Permit Issued
Issued on 12/5/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2022 APPLICANT
Assigned to Plan Check Engineer 9/14/2022 ARTIN ZARUKIAN
Corrections Issued 9/14/2022 ARTIN ZARUKIAN
Building Plans Picked Up 9/20/2022 APPLICANT
Plan Check Approved 11/29/2022 ROSENDO MEDINA
Issued 12/5/2022 APPLICANT
CofO in Progress 5/11/2023 JACK KARGODORIAN
Permit Finaled 5/11/2023 MICHAEL SMITH
CofO Issued 5/11/2023 MICHAEL SMITH
Permit Finaled 5/11/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/17/2022 COLIN LOREDO
Construction near power lines Cleared 11/17/2022 RIDWAN HARDY
Sewer availability Cleared 11/17/2022 COLIN LOREDO
ZI Cleared 11/17/2022 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 11/29/2022 COLIN LOREDO

Contact Information

Contractor Newform Construction Company; Lic. No.: 833302-B 7405 DEL ZURO DRIVE      LOS ANGELES, CA 90046

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/14/2022 Partial Inspection JOHN COLEMAN
Underground Mechanical 12/30/2022 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 1/11/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 1/11/2023 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 1/31/2023 Approved JACK KARGODORIAN
Green Building Rough 1/31/2023 Approved JACK KARGODORIAN
Insulation 2/7/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 2/7/2023 Approved CHRISTOPHE COCHRAN
Drywall Nailing 2/10/2023 Approved JACK KARGODORIAN
Shower Pan 2/15/2023 Approved JACK KARGODORIAN
ELECTRICAL-Final 4/3/2023 Approved JACK KARGODORIAN
Final 4/3/2023 Corrections Issued JACK KARGODORIAN
Green Building Final 4/3/2023 Approved JACK KARGODORIAN
PLUMBING-Final 4/3/2023 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 4/3/2023 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 4/3/2023 Approved JACK KARGODORIAN
Final 5/2/2023 Corrections Issued JOHN COLEMAN
PLUMBING-Final 5/2/2023 Partial Inspection JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 5/2/2023 SGSOV Approved JOHN COLEMAN
Final 5/11/2023 OK to Issue CofO JACK KARGODORIAN