10226 N MCCLEMONT AVE 91042
Certificate Information: 10226 N MCCLEMONT AVE 91042
- Application / Permit
- 22016-20000-27500
- Plan Check / Job No.
- B22VN13793
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/22/2022
- Issuing Office
- Current Status
- CofO Issued on 11/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2022 | SELLA BENYAMIN |
| Corrections Issued | 9/18/2022 | SELLA BENYAMIN |
| Plan Check Approved | 9/22/2022 | SELLA BENYAMIN |
| Issued | 9/22/2022 | APPLICANT |
| CofO in Progress | 10/20/2023 | WILLIAM WREN |
| Permit Finaled | 11/15/2023 | RUBEN SALAS |
| CofO Issued | 11/15/2023 | RUBEN SALAS |
| Permit Finaled | 11/15/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/19/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 9/19/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/28/2022 | Approved | WILLIAM WREN |
| Deputy Drilled-In Anchors | 2/10/2023 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 2/23/2023 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 2/23/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 2/23/2023 | Partial Approval | WILLIAM WREN |
| Deputy Drilled-In Anchors | 3/14/2023 | Conditional Approval | MICHAEL SMITH |
| BUILDING-Rough-Frame | 3/20/2023 | Not Ready for Inspection | WILLIAM WREN |
| Green Building Rough | 3/20/2023 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 3/20/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 4/14/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 4/14/2023 | Approved | WILLIAM WREN |
| Green Building Rough | 4/14/2023 | Not Ready for Inspection | WILLIAM WREN |
| HVAC-Rough | 4/14/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 4/14/2023 | Approved | WILLIAM WREN |
| Insulation | 5/1/2023 | Corrections Issued | WILLIAM WREN |
| Insulation | 5/5/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2023 | Approved | WILLIAM WREN |
| Insulation | 5/10/2023 | Not Ready for Inspection | WILLIAM WREN |
| Drywall Nailing | 5/18/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/18/2023 | Approved | MATTHEW NELSON |
| Shower Pan | 6/7/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 6/28/2023 | Approved | WILLIAM WREN |
| Sewer | 6/28/2023 | Approved | WILLIAM WREN |
| Smoke Detectors | 6/28/2023 | Approved | WILLIAM WREN |
| Underground Mechanical | 6/28/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 8/22/2023 | Approved | WILLIAM WREN |
| Final | 8/22/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 8/22/2023 | Approved | WILLIAM WREN |
| Green Building Rough | 8/22/2023 | Approved | WILLIAM WREN |
| HVAC-Final | 8/22/2023 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 8/22/2023 | SGSOV Approved | WILLIAM WREN |
| Final | 8/29/2023 | Corrections Issued | WILLIAM WREN |
| Service/Power Release | 8/29/2023 | Approved | WILLIAM WREN |
| Final | 9/29/2023 | OK to Issue CofO | WILLIAM WREN |