8750-8752 N GLORIA AVE 91343

Certificate Information: 8750-8752 N GLORIA AVE 91343

Application / Permit
22016-20000-27406
Plan Check / Job No.
B22VN13747
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing attached 20'x20' two car garage to Accessory Dwelling unit with new porch 5'x5' addition PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 12/1/2022
Issuing Office
Current Status
CofO Issued on 7/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2022 APPLICANT
Assigned to Plan Check Engineer 9/16/2022 MOHAMMAD ESMAILI
Corrections Issued 9/18/2022 MOHAMMAD ESMAILI
Plan Check Approved 11/8/2022 MOHAMMAD ESMAILI
Issued 12/1/2022 APPLICANT
CofO in Progress 7/17/2025 JENNIFER RABUCHIN
Permit Finaled 7/31/2025 RUBEN SALAS
CofO Issued 7/31/2025 RUBEN SALAS
Permit Finaled 7/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/22/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/22/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 9/22/2022 CARLOS AGUILERA
Sewer availability Cleared 9/22/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Van, Valkenburg, John; Lic. No.: C74939 13259 KISMET AVE      SYLMAR, CA 91342

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/19/2023 Partial Inspection JUAN VALENZUELA
Underground Mechanical 7/19/2023 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/28/2023 Approved RAUL OLAGI
PLUMBING-Rough 9/28/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 2/26/2024 No Access for Inspection MISAEL ESPARZA
Wood Frame 2/26/2024 No Access for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 2/28/2024 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/28/2024 Partial Approval RAUL OLAGI
Insulation 2/28/2024 Partial Approval RAUL OLAGI
HVAC-Rough 11/5/2024 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 11/5/2024 Partial Approval SALVADOR MARTINEZ
PLUMBING-Rough 11/5/2024 Corrections Issued SALVADOR MARTINEZ
Shower Pan 11/5/2024 Approved SALVADOR MARTINEZ
Special/Order Compliance 11/5/2024 Partial Inspection RAUL OLAGI
BUILDING-Rough-Frame 1/29/2025 Partial Approval SALVADOR MARTINEZ
HVAC-Rough 1/29/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 1/29/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 2/12/2025 Partial Approval GAREN HAYRAPETYAN
Green Building Rough 2/12/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 2/21/2025 Approved GAREN HAYRAPETYAN
Insulation 2/21/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 3/3/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 3/3/2025 Approved JENNIFER RABUCHIN
Pre-Inspection 4/18/2025 Approved LOUIS ESCOTO
Final 6/11/2025 Corrections Issued MICHAEL CORTEZ
Green Building Final 6/11/2025 Corrections Issued MICHAEL CORTEZ
PLUMBING-Final 6/11/2025 Corrections Issued MICHAEL CORTEZ
SGSOV-Seismic Gas S/O Valve 6/11/2025 SGSOV Approved MICHAEL CORTEZ
Smoke Detectors 6/11/2025 Approved MICHAEL CORTEZ
Final 6/24/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 6/24/2025 Corrections Issued SALVADOR MARTINEZ
Final 7/10/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 7/10/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 7/16/2025 Approved JENNIFER RABUCHIN
Final 7/16/2025 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 7/16/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/16/2025 Approved JENNIFER RABUCHIN