5725-5727 N RHEA AVE 91356
Certificate Information: 5725-5727 N RHEA AVE 91356
- Application / Permit
- 22016-20000-27405
- Plan Check / Job No.
- B22VN13746
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING GARAGE ATTTACHED TO SFD INTO AN ADU
- Permit Issued
- Issued on 8/6/2025
- Issuing Office
- Current Status
- CofO in Progress on 7/21/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2022 | SAMUEL GONZALEZ |
| Corrections Issued | 9/17/2022 | SAMUEL GONZALEZ |
| Plan Check Approved | 11/12/2022 | SAMUEL GONZALEZ |
| Issued | 8/6/2025 | APPLICANT |
| CofO in Progress | 7/21/2026 | JON MCHUGH |
Permit Application Clearance Information
| Address approval | Cleared | 11/7/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 11/7/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 11/8/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 11/8/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 11/8/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kiledjian,, George Zohrab; Lic. No.: C74761 | 11447 VIKING AVE NORTHRIDGE, CA 91326 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/8/2025 | Partial Approval | JON MCHUGH |
| Special/Order Compliance | 10/8/2025 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 11/14/2025 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 11/20/2025 | Partial Approval | JON MCHUGH |
| Deputy Reinf. Concrete | 11/25/2025 | Conditional Approval | JON MCHUGH |
| Insulation | 1/16/2026 | Partial Approval | JON MCHUGH |
| Wood Frame | 1/16/2026 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 2/26/2026 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2026 | Partial Approval | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 2/26/2026 | Corrections Issued | JON MCHUGH |
| Wood Frame | 2/26/2026 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 3/16/2026 | Approved | JON MCHUGH |
| HVAC-Rough | 3/16/2026 | Approved | JON MCHUGH |
| PLUMBING-Rough | 3/16/2026 | Approved | JON MCHUGH |
| Wood Frame | 3/16/2026 | Approved | JON MCHUGH |
| Insulation | 3/24/2026 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 3/24/2026 | Partial Approval | JON MCHUGH |
| Drywall Nailing | 3/31/2026 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 4/21/2026 | Approved | JON MCHUGH |
| Shower Pan | 4/21/2026 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 6/26/2026 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 6/26/2026 | Not Ready for Inspection | JON MCHUGH |
| Final | 6/26/2026 | Corrections Issued | JON MCHUGH |
| Green Building Final | 6/26/2026 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 6/26/2026 | Approved | JON MCHUGH |
| HVAC-Final | 6/26/2026 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Final | 6/26/2026 | Approved | JON MCHUGH |
| MERV13>=Rough | 6/26/2026 | Approved | JON MCHUGH |
| PLUMBING-Final | 6/26/2026 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/26/2026 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 6/26/2026 | Not Ready for Inspection | JON MCHUGH |
| Final | 7/1/2026 | Corrections Issued | JON MCHUGH |
| Service/Power Release | 7/1/2026 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 7/9/2026 | Approved | IVAN SARABIA |
| PLUMBING-Final | 7/9/2026 | Approved | IVAN SARABIA |
| Special/Order Compliance | 7/9/2026 | Partial Inspection | ROBERT GOLD |
| Final | 7/20/2026 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 7/20/2026 | Approved | JON MCHUGH |
| HVAC-Final | 7/20/2026 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 7/20/2026 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 7/20/2026 | Approved | JON MCHUGH |