8816 N WINNETKA AVE 91324

Certificate Information: 8816 N WINNETKA AVE 91324

Application / Permit
22016-20000-27203
Plan Check / Job No.
B22VN13642
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) 20' X 20' DETACHED GARAGE TO ACCESSSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 9/28/2022
Issuing Office
Current Status
CofO Issued on 6/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2022 APPLICANT
Assigned to Plan Check Engineer 9/9/2022 OMAR GARNICA
Corrections Issued 9/9/2022 OMAR GARNICA
Plan Check Approved 9/26/2022 OMAR GARNICA
Issued 9/28/2022 APPLICANT
CofO in Progress 5/4/2023 CHRIS CHRISTENSEN
Permit Finaled 6/30/2023 JOHN JANSON
CofO Issued 6/30/2023 JOHN JANSON
Permit Finaled 6/30/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/19/2022 LEE GUILBEAUX
Sewer availability Cleared 9/19/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/20/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/20/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/19/2022 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 10/27/2022 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 11/4/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 11/4/2022 Partial Approval CHRIS CHRISTENSEN
Special/Order Compliance 11/4/2022 Approved CHRIS CHRISTENSEN
Gas Test 11/18/2022 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 11/18/2022 Corrections Issued CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/30/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 11/30/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Gas Test 11/30/2022 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 11/30/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 11/30/2022 Approved CHRIS CHRISTENSEN
Sewer 11/30/2022 Approved CHRIS CHRISTENSEN
Underground Mechanical 11/30/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 12/9/2022 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 12/9/2022 Approved KRISTEN CAUSEY
HVAC-Rough 12/9/2022 Approved KRISTEN CAUSEY
Insulation 12/20/2022 Conditional Approval KRISTEN CAUSEY
Interior/Exterior Lathing 12/20/2022 Not Ready for Inspection KRISTEN CAUSEY
Drywall Nailing 12/22/2022 Approved JESUS PINEDA
Insulation 12/22/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 12/22/2022 Partial Approval JESUS PINEDA
Interior/Exterior Lathing 12/29/2022 Approved KRISTEN CAUSEY
Shower Pan 12/29/2022 Approved KRISTEN CAUSEY
Final 4/18/2023 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/18/2023 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 4/18/2023 Approved CHRIS CHRISTENSEN
Final 4/24/2023 Not Ready for Inspection MORRIS JACKSON
Final 4/28/2023 Conditional Approval CHRIS CHRISTENSEN
Green Building Final 4/28/2023 Approved CHRIS CHRISTENSEN
Final 5/3/2023 OK to Issue CofO CHRIS CHRISTENSEN