4567 W 17TH ST 90019
Certificate Information: 4567 W 17TH ST 90019
- Application / Permit
- 22016-20000-27181
- Plan Check / Job No.
- B22VN13631
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- ALTERATION TO INCREASE THE ROOF HEIGHT OF (E) DET. GARAGE PER DESIGN. "COMPLY WITH DEPARTMENT ORDER effective date 07/08/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 10/4/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2022 | LUIS RINCON |
| Corrections Issued | 9/13/2022 | LUIS RINCON |
| Building Plans Picked Up | 9/21/2022 | APPLICANT |
| Plan Check Approved | 9/29/2022 | ANGELICA MARTINEZ |
| Issued | 10/4/2022 | APPLICANT |
| CofO in Progress | 8/7/2023 | WILLIAM MICHALAK |
| CofO in Progress | 8/7/2023 | WILLIAM MICHALAK |
| CofO Issued | 8/18/2023 | BRUCE TODD |
| Permit Finaled | 8/18/2023 | BRUCE TODD |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Gemigniani,, Richard Louis; Lic. No.: C18783 | 4069 WOODCLIFF RD SHERMAN OAKS, CA 91403 |
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/22/2022 | Partial Approval | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 1/4/2023 | Approved | WILLIAM MICHALAK |
| Final | 3/1/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 3/8/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Final | 3/10/2023 | Corrections Issued | WILLIAM MICHALAK |
| METHANE-Final | 3/10/2023 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 3/10/2023 | SGSOV Approved | WILLIAM MICHALAK |
| Smoke Detectors | 3/10/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Wood Frame | 3/10/2023 | Approved | WILLIAM MICHALAK |
| Final | 3/14/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Smoke Detectors | 3/14/2023 | Approved | WILLIAM MICHALAK |
| Final | 6/14/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 8/7/2023 | OK to Issue CofO | WILLIAM MICHALAK |