20711-20713 W LEMAY ST 91306
Certificate Information: 20711-20713 W LEMAY ST 91306
- Application / Permit
- 22016-20000-27163
- Plan Check / Job No.
- B22VN13617
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 20' x 20' ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/18/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2022 | ANGELICA DAVE |
| Corrections Issued | 9/12/2022 | ANGELICA DAVE |
| Building Plans Picked Up | 9/13/2022 | APPLICANT |
| Issued | 10/18/2022 | APPLICANT |
| CofO in Progress | 4/11/2023 | ALEXANDER HANDY |
| Permit Finaled | 4/20/2023 | JOHN JANSON |
| CofO Issued | 4/20/2023 | JOHN JANSON |
| Permit Finaled | 4/20/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2022 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 9/14/2022 | KIRK LINKLATER |
| Sewer availability | Cleared | 9/14/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Pavlovich Construction Co; Lic. No.: 388868-B | 22817 VENTURA BLVD 1001 WOODLAND HILLS, CA 91364 |
| Engineer | Bui,, Mai Phuong; Lic. No.: C61280 | 7445 LURLINE AVE WINNETKA, CA 91306 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/7/2022 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 11/9/2022 | Corrections Issued | STEVEN BACK |
| Underground Mechanical | 11/9/2022 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 11/18/2022 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 11/18/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 11/18/2022 | Partial Approval | STEVEN BACK |
| Sewer | 11/18/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 12/9/2022 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 12/9/2022 | Corrections Issued | ALEXANDER HANDY |
| Green Building Rough | 12/9/2022 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 12/9/2022 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 12/9/2022 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 12/14/2022 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Corrections Issued | DAVID SANDOVAL |
| Insulation | 12/27/2022 | Partial Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 12/30/2022 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2022 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 12/30/2022 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 12/30/2022 | Approved | ALEXANDER HANDY |
| Shower Pan | 12/30/2022 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 1/4/2023 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 1/4/2023 | Approved | KRISTEN CAUSEY |
| Final | 4/5/2023 | Corrections Issued | HORACE FULTZ |
| Green Building Final | 4/5/2023 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Approved | HORACE FULTZ |
| Smoke Detectors | 4/5/2023 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 4/10/2023 | Approved | ALEXANDER HANDY |
| Final | 4/10/2023 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 4/10/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 4/10/2023 | Approved | ALEXANDER HANDY |
| Service/Power Release | 4/10/2023 | Approved | ALEXANDER HANDY |