4876 1/2 N WICOPEE AVE 90041

Certificate Information: 4876 1/2 N WICOPEE AVE 90041

Application / Permit
22016-20000-27021
Plan Check / Job No.
B22VN13531
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) W/ EXTERIOR MODIFICATION PER PLAN. ALL WORK PER WFPP.
Permit Issued
Issued on 3/17/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2022 APPLICANT
Assigned to Plan Check Engineer 9/9/2022 HAYATO TSUCHIYA
Corrections Issued 9/13/2022 HAYATO TSUCHIYA
Building Plans Picked Up 9/22/2022 APPLICANT
Applicant returned to address corrections 1/24/2023 RAMA DABADGE
Plan Check Approved 2/28/2023 ALEC MOUSAKHANIAN
Issued 3/17/2023 APPLICANT
CofO in Progress 4/8/2024 CRAIG VAUGHAN
Permit Finaled 4/8/2024 DEROLD HAUFF
CofO Issued 4/8/2024 DEROLD HAUFF
Permit Finaled 4/8/2024 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 10/1/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/4/2022 STEVE MELGAR
Hydrant and Access approval Cleared 11/18/2022 KURT CORRAL
Grading Pre-Inspection Cleared 11/21/2022 KIRK LINKLATER
Address approval Cleared 1/23/2023 TREVOR QUAN

Contact Information

Architect Gilliam,, Jonathan; Lic. No.: C33995 15017 ARCHWOOD STREET      VAN NUYS, CA 91405
Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/24/2023 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/18/2023 Partial Approval CRAIG VAUGHAN
Underground Mechanical 4/18/2023 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 5/5/2023 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 5/11/2023 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 5/18/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 7/31/2023 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 7/31/2023 Approved SCOTT FINNILA
MERV13>=Rough 7/31/2023 Approved SCOTT FINNILA
PLUMBING-Rough 7/31/2023 Approved SCOTT FINNILA
BUILDING-Rough-Frame 8/10/2023 Conditional Approval BRIAN SULLIVAN
HVAC-Rough 8/10/2023 Approved BRIAN SULLIVAN
Insulation 8/10/2023 Not Ready for Inspection BRIAN SULLIVAN
Insulation 9/19/2023 Approved ROY SPAULDING
Interior/Exterior Lathing 9/19/2023 Approved ROY SPAULDING
Drywall Nailing 10/30/2023 Approved JOSH MEISTER
Shower Pan 10/30/2023 Approved JOSH MEISTER
BUILDING-Rough-Frame 3/29/2024 Approved CRAIG VAUGHAN
ELECTRICAL-Final 3/29/2024 Approved CRAIG VAUGHAN
Final 3/29/2024 Corrections Issued CRAIG VAUGHAN
HVAC-Final 3/29/2024 Corrections Issued CRAIG VAUGHAN
MERV13>=Final 3/29/2024 Approved CRAIG VAUGHAN
PLUMBING-Final 3/29/2024 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 3/29/2024 SGSOV Not Required CRAIG VAUGHAN
Smoke Detectors 3/29/2024 Approved CRAIG VAUGHAN
Final 4/5/2024 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 4/5/2024 Approved CRAIG VAUGHAN
PLUMBING-Final 4/5/2024 Approved CRAIG VAUGHAN