7712 N FERNCOLA AVE 91352

Certificate Information: 7712 N FERNCOLA AVE 91352

Application / Permit
22016-20000-26959
Plan Check / Job No.
B22VN13514
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 11'-10" X 20'-5" OF (E) CHICKEN HOUSE CREATING A 29'-2" X 20'-5" ACCESSORY DWELLING UNIT PER GCS 65852.2 (e) (1) (A).
Permit Issued
Issued on 10/27/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2022 APPLICANT
Corrections Issued 9/10/2022 SERGIO MUNIZ
Assigned to Plan Check Engineer 9/12/2022 SERGIO MUNIZ
Building Plans Picked Up 9/16/2022 APPLICANT
Corrections Issued 9/29/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 9/29/2022 DANIEL ABRAMYAN
Plan Check Approved 10/12/2022 ALEC MOUSAKHANIAN
Issued 10/27/2022 APPLICANT
CofO in Progress 8/21/2023 DAVID ANDERSON
Permit Finaled 10/15/2023 RUBEN SALAS
CofO Issued 10/15/2023 RUBEN SALAS
Permit Finaled 10/15/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/19/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 9/19/2022 COLIN LOREDO
Sewer availability Cleared 9/19/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Valencia,, Byron Steve; Lic. No.: C87372 14537 VENTURA BLVD      SHERMAN OAKS, CA 91403

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/17/2022 Corrections Issued DAVID ANDERSON
Pre-Inspection 11/17/2022 Approved DAVID ANDERSON
Deputy Drilled-In Anchors 2/8/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 2/8/2023 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 2/8/2023 Partial Approval DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 2/21/2023 No Access for Inspection DAVID ANDERSON
Footing/Foundation/Slab 2/21/2023 No Access for Inspection DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 3/3/2023 Approved DAVID ANDERSON
Footing/Foundation/Slab 3/3/2023 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 3/31/2023 Corrections Issued DAVID ANDERSON
Wood Frame 3/31/2023 Partial Approval DAVID ANDERSON
Deputy Wood Construction 4/3/2023 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 4/14/2023 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/14/2023 Partial Approval DAVID ANDERSON
Gas Test 4/14/2023 Approved DAVID ANDERSON
Underground Mechanical 4/14/2023 Partial Approval DAVID ANDERSON
ELECTRICAL-Rough 4/24/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 5/1/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 5/19/2023 Approved DAVID ANDERSON
HVAC-Rough 5/19/2023 Approved DAVID ANDERSON
PLUMBING-Rough 5/19/2023 Approved DAVID ANDERSON
Insulation 6/2/2023 Approved DAVID ANDERSON
Drywall Nailing 6/9/2023 Approved DAVID ANDERSON
Final 7/14/2023 Corrections Issued DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 7/14/2023 SGSOV Approved DAVID ANDERSON
Smoke Detectors 7/14/2023 Not Ready for Inspection DAVID ANDERSON
Final 8/18/2023 OK to Issue CofO DAVID ANDERSON
Smoke Detectors 8/18/2023 Approved DAVID ANDERSON