12621 W MARTHA ST 91607
Certificate Information: 12621 W MARTHA ST 91607
- Application / Permit
- 22016-20000-26710
- Plan Check / Job No.
- B22VN13384
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONVERT (E) 2-CAR GARAGE and STORAGE WITH ADDITION INTO ADU PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 11/16/2022
- Issuing Office
- Current Status
- Issued on 11/16/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2022 | KHUONG TRUONG |
| Corrections Issued | 9/10/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 10/20/2022 | KHUONG TRUONG |
| Plan Check Approved | 11/14/2022 | JOSEPH RAFOLS |
| Issued | 11/16/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 9/16/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/19/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 11/8/2022 | RIDWAN HARDY |
Contact Information
| Architect | Deloache,, Scott Stephenson; Lic. No.: C30665 | 1157 S BUNDY DR #303 LOS ANGELES, CA 90049 |
| Contractor | Kaiser Comm Construction Inc; Lic. No.: 1011938-B | , |
| Engineer | Karapetian,, Arbi; Lic. No.: C79953 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/7/2022 | Conditional Approval | ROBERT GOLD |
| PLUMBING-Rough | 12/14/2022 | Approved | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 12/19/2022 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 2/1/2023 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 2/7/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 2/21/2023 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 2/21/2023 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 2/21/2023 | Not Ready for Inspection | KIRK SANDERS |
| Insulation | 2/21/2023 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 2/21/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/15/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 3/15/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/15/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 3/15/2023 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/1/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 5/1/2023 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 5/1/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/17/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 5/17/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 5/17/2023 | Approved | KIRK SANDERS |
| Insulation | 5/25/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/25/2023 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 7/13/2023 | Corrections Issued | KIRK SANDERS |
| Drywall Nailing | 7/20/2023 | Partial Approval | KIRK SANDERS |
| Drywall Nailing | 8/9/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 12/1/2023 | Approved | MEL KHACHATOURIAN |
| HVAC-Final | 12/1/2023 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 12/1/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Final | 1/22/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 1/22/2024 | Approved | JOSE AVILA |
| Green Building Final | 1/22/2024 | Not Ready for Inspection | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/22/2024 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 1/22/2024 | Approved | JOSE AVILA |
| Final | 2/9/2024 | Corrections Issued | JOSE AVILA |
| Green Building Final | 2/9/2024 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/9/2024 | SGSOV Approved | JOSE AVILA |
| Final | 2/14/2024 | Corrections Issued | JOSE AVILA |
| Final | 2/16/2024 | Partial Approval | JOSE AVILA |
| Service/Power Release | 3/1/2024 | Approved | JOSE AVILA |