23718-23720 W GERRAD WAY 91307
Certificate Information: 23718-23720 W GERRAD WAY 91307
- Application / Permit
- 22016-20000-26628
- Plan Check / Job No.
- B22VN13335
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Convert existing attached 2 car garage to new A.D.U per GCS 65852.2(e)(1)(A), all work per WFPP
- Permit Issued
- Issued on 5/17/2023
- Issuing Office
- Current Status
- CofO Issued on 6/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2022 | MINA HABILI |
| Corrections Issued | 10/5/2022 | MINA HABILI |
| Applicant returned to address corrections | 5/3/2023 | MINA HABILI |
| Plan Check Approved | 5/3/2023 | MINA HABILI |
| No Progress | 5/3/2023 | MINA HABILI |
| Plan Check Approved | 5/11/2023 | MINA HABILI |
| Issued | 5/17/2023 | APPLICANT |
| CofO in Progress | 5/29/2026 | JEFFREY HARTLINE |
| Permit Finaled | 6/10/2026 | JOHN JANSON |
| CofO Issued | 6/10/2026 | JOHN JANSON |
| Permit Finaled | 6/10/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/3/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 11/3/2022 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 11/15/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/26/2024 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 10/28/2024 | No Access for Inspection | CHRIS CHRISTENSEN |
| Pre-Inspection | 10/30/2024 | Partial Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 4/8/2025 | Corrections Issued | SCOTT SOBEL |
| Excavation/Setback/Form/Re-Bar | 4/8/2025 | Corrections Issued | SCOTT SOBEL |
| PLUMBING-Rough | 4/8/2025 | Corrections Issued | SCOTT SOBEL |
| Deputy Drilled-In Anchors | 5/13/2025 | Conditional Approval | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 6/4/2025 | Approved | JEFFREY HARTLINE |
| Special/Order Compliance | 6/4/2025 | Corrections Issued | JEFFREY HARTLINE |
| Underground Mechanical | 6/4/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2025 | Partial Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 6/30/2025 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 6/30/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| PLUMBING-Rough | 6/30/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 7/23/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 7/23/2025 | Partial Approval | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 7/23/2025 | Partial Approval | JEFFREY HARTLINE |
| Rough-Elec/Plmb/HVAC | 7/23/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 7/31/2025 | Corrections Issued | JEFFREY HARTLINE |
| Insulation | 8/8/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 8/19/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 8/19/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 8/25/2025 | Approved | JEFFREY HARTLINE |
| Final | 5/6/2026 | Corrections Issued | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 5/6/2026 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 5/6/2026 | Approved | JEFFREY HARTLINE |
| Final | 5/29/2026 | OK to Issue CofO | JEFFREY HARTLINE |