10045-10047 N LEMONA AVE 91345

Certificate Information: 10045-10047 N LEMONA AVE 91345

Application / Permit
22016-20000-26595
Plan Check / Job No.
B22VN13309
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Junior Accessory Dwelling Unit
Work Description
CONVERT THE (E) ATTACHED GARAGE TO A NEW 22'-1" x 22'-2" JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.229. ALL WORK PER WFPP.
Permit Issued
Issued on 9/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2022 APPLICANT
Assigned to Plan Check Engineer 9/7/2022 SERGIO MUNIZ
Corrections Issued 9/8/2022 SERGIO MUNIZ
Building Plans Picked Up 9/14/2022 APPLICANT
Plan Check Approved 9/27/2022 SARKIS HARABEDIAN
Issued 9/27/2022 APPLICANT
CofO in Progress 3/16/2023 JENNIFER RABUCHIN
Permit Finaled 4/4/2023 DANIEL ORRANTE
CofO Issued 4/4/2023 DANIEL ORRANTE
Permit Finaled 4/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 9/15/2022 LUCIA MERCADO
Address approval Cleared 9/16/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/16/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 9/22/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/6/2022 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 10/12/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 10/12/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 11/8/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/8/2022 Not Ready for Inspection JENNIFER RABUCHIN
Wood Frame 11/8/2022 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/6/2022 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/6/2022 Approved JENNIFER RABUCHIN
Green Building Rough 12/6/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 12/6/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 12/6/2022 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 12/16/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 12/29/2022 Approved RYAN SALAZAR
HVAC-Rough 12/29/2022 Partial Approval RYAN SALAZAR
Shower Pan 12/29/2022 Approved RYAN SALAZAR
Insulation 1/9/2023 Corrections Issued RAUL OLAGI
Drywall Nailing 1/11/2023 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 1/11/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 1/13/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 1/19/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/8/2023 Approved JENNIFER RABUCHIN
Final 3/8/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/8/2023 Approved JENNIFER RABUCHIN
Green Building Rough 3/8/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 3/8/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/13/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Final 3/13/2023 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Final 3/13/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 3/13/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 3/15/2023 Approved JENNIFER RABUCHIN
Final 3/15/2023 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 3/15/2023 Approved JENNIFER RABUCHIN
HVAC-Final 3/15/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/15/2023 Approved JENNIFER RABUCHIN