686 3/4 E 42ND ST 90011
Certificate Information: 686 3/4 E 42ND ST 90011
- Application / Permit
- 22016-20000-26553
- Plan Check / Job No.
- B22VN13296
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE AND ADDITION TO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (g)
- Permit Issued
- Issued on 8/25/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/7/2022 | JESSE ARELLANO |
| Corrections Issued | 9/8/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 10/19/2022 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 10/26/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 10/26/2022 | PINANK PATEL |
| Issued | 8/25/2023 | APPLICANT |
| Refund in Progress | 4/23/2025 | SELENIA GARCIA |
| Refund Withdrawn | 4/29/2025 | SUZY TER-OGANESYAN |
| Issued | 4/29/2025 | SUZY TER-OGANESYAN |
| CofO in Progress | 1/27/2026 | ALEJANDRO DE ARTOLA |
| No Progress | 1/28/2026 | MICHAEL LEWIS |
| CofO in Progress | 1/28/2026 | MICHAEL LEWIS |
| Permit Finaled | 1/28/2026 | DEROLD HAUFF |
| CofO Issued | 1/28/2026 | DEROLD HAUFF |
| Permit Finaled | 1/28/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/19/2022 | AMAAN MALIK |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2024 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 5/1/2025 | Not Ready for Inspection | JOSE MACIAS |
| Pre-Inspection | 5/1/2025 | Approved | JOSE MACIAS |
| Underground Mechanical | 5/7/2025 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 5/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 5/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 5/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/23/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Gas Test | 7/23/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/23/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/30/2025 | Corrections Issued | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 8/11/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 8/11/2025 | Corrections Issued | LUIS CASTRO |
| BUILDING-Rough-Frame | 8/15/2025 | Approved | WAYNE REGESTER |
| Green Building Rough | 8/15/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 8/15/2025 | Approved | WAYNE REGESTER |
| Insulation | 8/29/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/29/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 9/18/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 9/24/2025 | Approved | RONNIE MEDINA |
| ELECTRICAL-Final | 11/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 11/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/6/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/20/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 1/20/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 1/20/2026 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/20/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/20/2026 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 1/20/2026 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/22/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/22/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/22/2026 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/26/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/26/2026 | OK to Issue CofO | ALEJANDRO DE ARTOLA |