686 3/4 E 42ND ST 90011

Certificate Information: 686 3/4 E 42ND ST 90011

Application / Permit
22016-20000-26553
Plan Check / Job No.
B22VN13296
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND ADDITION TO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (g)
Permit Issued
Issued on 8/25/2023
Issuing Office
Valley
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2022 APPLICANT
Assigned to Plan Check Engineer 9/7/2022 JESSE ARELLANO
Corrections Issued 9/8/2022 JESSE ARELLANO
Applicant returned to address corrections 10/19/2022 MIROOSH KHACHATOORIAN
Plan Check Approved 10/26/2022 LUISANGEL VALENZUELA
Plan Check Approved 10/26/2022 PINANK PATEL
Issued 8/25/2023 APPLICANT
Refund in Progress 4/23/2025 SELENIA GARCIA
Refund Withdrawn 4/29/2025 SUZY TER-OGANESYAN
Issued 4/29/2025 SUZY TER-OGANESYAN
CofO in Progress 1/27/2026 ALEJANDRO DE ARTOLA
No Progress 1/28/2026 MICHAEL LEWIS
CofO in Progress 1/28/2026 MICHAEL LEWIS
Permit Finaled 1/28/2026 DEROLD HAUFF
CofO Issued 1/28/2026 DEROLD HAUFF
Permit Finaled 1/28/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/19/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 10/19/2022 CARLOS AGUILERA
Sewer availability Cleared 10/19/2022 AMAAN MALIK

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/3/2024 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 5/1/2025 Not Ready for Inspection JOSE MACIAS
Pre-Inspection 5/1/2025 Approved JOSE MACIAS
Underground Mechanical 5/7/2025 Partial Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 5/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 5/14/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 5/22/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 5/28/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/26/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/23/2025 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Partial Approval ALEJANDRO DE ARTOLA
Gas Test 7/23/2025 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 7/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/24/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/30/2025 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Rough 8/11/2025 Approved LUIS CASTRO
HVAC-Rough 8/11/2025 Corrections Issued LUIS CASTRO
BUILDING-Rough-Frame 8/15/2025 Approved WAYNE REGESTER
Green Building Rough 8/15/2025 Approved WAYNE REGESTER
HVAC-Rough 8/15/2025 Approved WAYNE REGESTER
Insulation 8/29/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 8/29/2025 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 9/18/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 9/24/2025 Approved RONNIE MEDINA
ELECTRICAL-Final 11/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 11/4/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 11/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 11/6/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 11/12/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 1/20/2026 Corrections Issued ALEJANDRO DE ARTOLA
Final 1/20/2026 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 1/20/2026 Approved ALEJANDRO DE ARTOLA
HVAC-Final 1/20/2026 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 1/20/2026 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 1/20/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 1/22/2026 Approved ALEJANDRO DE ARTOLA
Final 1/22/2026 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 1/22/2026 SGSOV Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 1/26/2026 Approved ALEJANDRO DE ARTOLA
Final 1/26/2026 OK to Issue CofO ALEJANDRO DE ARTOLA