9508-9512 N NATICK AVE 91343

Certificate Information: 9508-9512 N NATICK AVE 91343

Application / Permit
22016-20000-26378
Plan Check / Job No.
B22VN13204
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO JR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22 IN (E) SFD.
Permit Issued
Issued on 9/23/2022
Issuing Office
Current Status
CofO Issued on 2/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2022 APPLICANT
Assigned to Plan Check Engineer 9/7/2022 JESSE ARELLANO
Corrections Issued 9/8/2022 JESSE ARELLANO
Building Plans Picked Up 9/12/2022 APPLICANT
Plan Check Approved 9/23/2022 SERGIO MUNIZ
Issued 9/23/2022 APPLICANT
CofO in Progress 11/21/2023 JENNIFER RABUCHIN
Permit Finaled 2/14/2024 RUBEN SALAS
CofO Issued 2/14/2024 RUBEN SALAS
Permit Finaled 2/14/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/12/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 9/12/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 9/13/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 9/13/2022 JOSE DUARTE-DIAZ
Public Works-Open Permits Cleared 9/13/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 9/13/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Rough-Elec/Plmb/HVAC 12/13/2022 Partial Approval JENNIFER RABUCHIN
Sewer 12/13/2022 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 12/15/2022 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 12/20/2022 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 1/11/2023 Partial Approval JENNIFER RABUCHIN
Wood Frame 1/13/2023 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/1/2023 Partial Inspection JOHN COLEMAN
ELECTRICAL-Rough 2/1/2023 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 2/1/2023 Approved JOHN COLEMAN
Gas Test 2/1/2023 Approved JOHN COLEMAN
HVAC-Rough 2/1/2023 Approved JOHN COLEMAN
PLUMBING-Rough 2/1/2023 Approved JOHN COLEMAN
BUILDING-Rough-Frame 2/9/2023 Approved JENNIFER RABUCHIN
Green Building Rough 2/9/2023 Approved JENNIFER RABUCHIN
Insulation 2/9/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/9/2023 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 2/21/2023 Approved JENNIFER RABUCHIN
Shower Pan 2/21/2023 Corrections Issued JENNIFER RABUCHIN
Shower Pan 2/27/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/12/2023 Corrections Issued JENNIFER RABUCHIN
Final 10/12/2023 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 10/12/2023 Approved JENNIFER RABUCHIN
HVAC-Final 10/12/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/12/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/12/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 10/12/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/17/2023 Approved JENNIFER RABUCHIN
Final 10/17/2023 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 10/17/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/17/2023 Approved JENNIFER RABUCHIN