8545 N GLORIA AVE 91343

Certificate Information: 8545 N GLORIA AVE 91343

Application / Permit
22016-20000-26207
Plan Check / Job No.
B22VN13159
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL, REROOFING, ADD & REPLACE DOORS/WINDOWS PER PLANS.
Permit Issued
Issued on 9/30/2022
Issuing Office
Valley
Current Status
Permit Finaled on 5/30/2023

Permit Application Status History

Submitted 8/29/2022 APPLICANT
Assigned to Plan Check Engineer 9/2/2022 ARTIN ZARUKIAN
Corrections Issued 9/3/2022 ARTIN ZARUKIAN
Building Plans Picked Up 9/9/2022 APPLICANT
Plan Check Approved 9/30/2022 LUIS RINCON
Issued 9/30/2022 APPLICANT
Permit Finaled 5/30/2023 RAUL OLAGI

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/14/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 12/8/2022 Partial Inspection RAUL OLAGI
PLUMBING-Rough 12/8/2022 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 12/13/2022 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 12/13/2022 Approved RAUL OLAGI
PLUMBING-Rough 12/13/2022 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 12/23/2022 Approved RAUL OLAGI
PLUMBING-Rough 12/23/2022 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 1/3/2023 Partial Approval RAUL OLAGI
Green Building Rough 1/3/2023 Approved RAUL OLAGI
PLUMBING-Rough 1/3/2023 Approved RAUL OLAGI
Insulation 1/4/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 1/4/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 1/18/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 1/18/2023 Partial Approval RAUL OLAGI
Drywall Nailing 1/30/2023 Approved RAUL OLAGI
Shower Pan 3/29/2023 Approved RAUL OLAGI
Final 5/30/2023 Permit Finaled RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/30/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 5/30/2023 Approved RAUL OLAGI