13499-13501 W EBELL ST 91402

Certificate Information: 13499-13501 W EBELL ST 91402

Application / Permit
22016-20000-25917
Plan Check / Job No.
B22VN13082
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan convert (E) attached garage in to an ADU PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 9/9/2022
Issuing Office
Current Status
CofO Issued on 4/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 KHUONG TRUONG
Corrections Issued 9/2/2022 KHUONG TRUONG
Plan Check Approved 9/8/2022 ADAM HEGAZI
Issued 9/9/2022 APPLICANT
CofO in Progress 4/12/2023 GREGG CUMMINGS
Permit Finaled 4/12/2023 MICHAEL SMITH
CofO Issued 4/12/2023 MICHAEL SMITH
Permit Finaled 4/12/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/7/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 9/7/2022 ROMAN GUTIERREZ
Sewer availability Cleared 9/7/2022 ROMAN GUTIERREZ

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor K M Builders; Lic. No.: 1080573-B       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/6/2022 Conditional Approval GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 10/13/2022 Approved WILLIAM WREN
Footing/Foundation/Slab 10/13/2022 Approved WILLIAM WREN
PLUMBING-Rough 10/13/2022 Partial Approval WILLIAM WREN
Sewer 10/13/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 11/29/2022 Partial Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 11/29/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 11/29/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 12/6/2022 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 12/6/2022 Partial Approval GREGG CUMMINGS
Green Building Rough 12/6/2022 Approved GREGG CUMMINGS
Rough-Elec/Plmb/HVAC 12/6/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 12/14/2022 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 12/14/2022 Approved MATTHEW NELSON
Insulation 12/16/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 12/21/2022 Approved GREGG CUMMINGS
Insulation 12/27/2022 Approved GREGG CUMMINGS
Shower Pan 12/27/2022 Not Ready for Inspection GREGG CUMMINGS
Drywall Nailing 1/9/2023 Approved GREGG CUMMINGS
Shower Pan 1/13/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 1/18/2023 Approved GREGG CUMMINGS
ELECTRICAL-Final 3/20/2023 Approved CHRISTOPHER DELLEFIELD
Final 3/20/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 3/20/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 3/20/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 3/20/2023 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 3/20/2023 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Smoke Detectors 3/20/2023 Approved CHRISTOPHER DELLEFIELD
Final 3/28/2023 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 3/28/2023 SGSOV Approved GREGG CUMMINGS
Final 4/11/2023 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 4/11/2023 Approved GREGG CUMMINGS
PLUMBING-Final 4/11/2023 Approved GREGG CUMMINGS