5514 N SIMPSON AVE 91607

Certificate Information: 5514 N SIMPSON AVE 91607

Application / Permit
22016-20000-25807
Plan Check / Job No.
B22VN13023
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert existing 2-car garage (18'x20') and existing Storage (22'x14'-4") into a 1-bedroom ADU (total conversion 675 sf) PER STATE LAW
Permit Issued
Issued on 9/16/2022
Issuing Office
Current Status
CofO Issued on 4/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2022 APPLICANT
Assigned to Plan Check Engineer 8/31/2022 KHUONG TRUONG
Corrections Issued 8/31/2022 KHUONG TRUONG
Applicant returned to address corrections 9/6/2022 KHUONG TRUONG
Plan Check Approved 9/15/2022 KHUONG TRUONG
Issued 9/16/2022 APPLICANT
CofO in Progress 3/17/2023 JACK KARGODORIAN
CofO Issued 4/6/2023 MICHAEL SMITH
Permit Finaled 4/6/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/2/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 9/2/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 9/2/2022 JOSE DUARTE-DIAZ
Specific Plan Cleared 9/2/2022 CORREY KITCHENS
ZI Cleared 9/2/2022 CORREY KITCHENS
Public Works-Highway Ded. Cleared 9/2/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 9/2/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Flip It Homes Inc; Lic. No.: 1043456-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 10/26/2022 Corrections Issued JACK KARGODORIAN
Underground Mechanical 10/26/2022 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 11/1/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Partial Approval JACK KARGODORIAN
Underground Mechanical 11/28/2022 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 12/2/2022 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 12/2/2022 Approved JOHN COLEMAN
HVAC-Rough 12/2/2022 Approved JOHN COLEMAN
MERV13>=Rough 12/2/2022 Approved JOHN COLEMAN
PLUMBING-Rough 12/2/2022 Approved JOHN COLEMAN
Deputy Wood Construction 12/9/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 12/9/2022 Approved JACK KARGODORIAN
Insulation 12/9/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 12/9/2022 Partial Approval JACK KARGODORIAN
Underground Mechanical 12/9/2022 Approved JACK KARGODORIAN
Drywall Nailing 12/19/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 12/19/2022 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 12/21/2022 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 12/21/2022 Not Ready for Inspection JENNIFER RABUCHIN
Final 12/21/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Final 12/21/2022 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Final 12/21/2022 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Final 12/21/2022 Not Ready for Inspection JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/21/2022 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 12/21/2022 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/13/2023 Approved JACK KARGODORIAN
ELECTRICAL-Final 3/13/2023 Not Ready for Inspection JACK KARGODORIAN
Final 3/13/2023 Corrections Issued JACK KARGODORIAN
HVAC-Final 3/13/2023 Approved JACK KARGODORIAN
MERV13>=Final 3/13/2023 Approved JACK KARGODORIAN
PLUMBING-Final 3/13/2023 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/13/2023 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 3/13/2023 Approved JACK KARGODORIAN
ELECTRICAL-Final 3/17/2023 Approved JACK KARGODORIAN
Final 3/17/2023 OK to Issue CofO JACK KARGODORIAN
PLUMBING-Final 3/17/2023 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/17/2023 SGSOV Approved JACK KARGODORIAN