5514 N SIMPSON AVE 91607
Certificate Information: 5514 N SIMPSON AVE 91607
- Application / Permit
- 22016-20000-25807
- Plan Check / Job No.
- B22VN13023
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert existing 2-car garage (18'x20') and existing Storage (22'x14'-4") into a 1-bedroom ADU (total conversion 675 sf) PER STATE LAW
- Permit Issued
- Issued on 9/16/2022
- Issuing Office
- Current Status
- CofO Issued on 4/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2022 | KHUONG TRUONG |
| Corrections Issued | 8/31/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 9/6/2022 | KHUONG TRUONG |
| Plan Check Approved | 9/15/2022 | KHUONG TRUONG |
| Issued | 9/16/2022 | APPLICANT |
| CofO in Progress | 3/17/2023 | JACK KARGODORIAN |
| CofO Issued | 4/6/2023 | MICHAEL SMITH |
| Permit Finaled | 4/6/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/2/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 9/2/2022 | JOSE DUARTE-DIAZ |
| Specific Plan | Cleared | 9/2/2022 | CORREY KITCHENS |
| ZI | Cleared | 9/2/2022 | CORREY KITCHENS |
| Public Works-Highway Ded. | Cleared | 9/2/2022 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 9/2/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | Corrections Issued | JACK KARGODORIAN |
| Underground Mechanical | 10/26/2022 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 11/1/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 11/28/2022 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 12/2/2022 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 12/2/2022 | Approved | JOHN COLEMAN |
| HVAC-Rough | 12/2/2022 | Approved | JOHN COLEMAN |
| MERV13>=Rough | 12/2/2022 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 12/2/2022 | Approved | JOHN COLEMAN |
| Deputy Wood Construction | 12/9/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2022 | Approved | JACK KARGODORIAN |
| Insulation | 12/9/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/9/2022 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 12/9/2022 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 12/19/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/19/2022 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 12/21/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/21/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 12/21/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Final | 12/21/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Final | 12/21/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/21/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/21/2022 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 12/21/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/13/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 3/13/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 3/13/2023 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 3/13/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 3/13/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 3/13/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/13/2023 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 3/13/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 3/17/2023 | Approved | JACK KARGODORIAN |
| Final | 3/17/2023 | OK to Issue CofO | JACK KARGODORIAN |
| PLUMBING-Final | 3/17/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/17/2023 | SGSOV Approved | JACK KARGODORIAN |