10346-10348 N RUFFNER AVE 91344
Certificate Information: 10346-10348 N RUFFNER AVE 91344
- Application / Permit
- 22016-20000-25647
- Plan Check / Job No.
- B22VN12953
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING GARAGE TO ADU.
- Permit Issued
- Issued on 9/23/2022
- Issuing Office
- Current Status
- CofO Issued on 4/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2022 | JOE VO |
| Corrections Issued | 8/31/2022 | JOE VO |
| Plan Check Approved | 9/14/2022 | JOE VO |
| Issued | 9/23/2022 | APPLICANT |
| CofO in Progress | 3/14/2023 | JAVIER RAMOS JR |
| Permit Finaled | 4/3/2023 | MICHAEL SMITH |
| CofO Issued | 4/3/2023 | MICHAEL SMITH |
| Permit Finaled | 4/3/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 8/31/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 9/2/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 9/2/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 9/2/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Socal Remodeling; Lic. No.: 1050297-B | , |
| Engineer | Yeghiayan,, Armond; Lic. No.: NA69935 | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/28/2022 | Approved | DEANDRE HOFFMAN |
| PLUMBING-Rough | 9/28/2022 | Partial Approval | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 10/7/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 10/7/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 10/7/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Pre-Inspection | 10/7/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/14/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 11/14/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 11/14/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 11/14/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 11/14/2022 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 11/14/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/18/2022 | Corrections Issued | ROBERT GOLD |
| ELECTRICAL-Rough | 11/18/2022 | Corrections Issued | ROBERT GOLD |
| Green Building Rough | 11/18/2022 | Approved | ROBERT GOLD |
| HVAC-Rough | 11/18/2022 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Rough | 11/18/2022 | Approved | ROBERT GOLD |
| ELECTRICAL-Rough | 11/29/2022 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 11/29/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/7/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 12/7/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 12/7/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 12/7/2022 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/7/2022 | Partial Approval | JAVIER RAMOS JR |
| Wood Frame | 12/7/2022 | Partial Approval | JAVIER RAMOS JR |
| Deputy Wood Construction | 12/13/2022 | Conditional Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/14/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 12/14/2022 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 12/14/2022 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 12/14/2022 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 12/20/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/20/2022 | Approved | JAVIER RAMOS JR |
| Sewer | 12/20/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 12/20/2022 | Approved | JAVIER RAMOS JR |
| Gas Test | 1/20/2023 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 1/20/2023 | Partial Approval | JAVIER RAMOS JR |
| Service/Power Release | 2/8/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/15/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 2/15/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 2/15/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 2/15/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Final | 2/15/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/15/2023 | SGSOV Not Ready | JAVIER RAMOS JR |
| Smoke Detectors | 2/15/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 2/23/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 2/23/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/23/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 2/23/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 3/2/2023 | Approved | JAVIER RAMOS JR |
| Final | 3/2/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 3/2/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 3/2/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 3/2/2023 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 3/2/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 3/14/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 3/14/2023 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 3/14/2023 | Approved | JAVIER RAMOS JR |