16448-16450 W TULSA ST 91344
Certificate Information: 16448-16450 W TULSA ST 91344
- Application / Permit
- 22016-20000-24959
- Plan Check / Job No.
- B22VN12655
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT (372 SQ FT) PER LAMC 12.22 A.33(c) and (e). REFRAME ROOF ABOVE PROPOSED ADU
- Permit Issued
- Issued on 10/5/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2022 | LUIS RINCON |
| Corrections Issued | 8/30/2022 | LUIS RINCON |
| Building Plans Picked Up | 9/8/2022 | APPLICANT |
| Plan Check Approved | 10/5/2022 | JEROME MAGAT PALMA |
| Issued | 10/5/2022 | APPLICANT |
| CofO in Progress | 3/16/2023 | JAVIER RAMOS JR |
| Permit Finaled | 4/12/2023 | MICHAEL SMITH |
| CofO Issued | 4/12/2023 | MICHAEL SMITH |
| Permit Finaled | 4/12/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/12/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/12/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/9/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 12/9/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/9/2022 | Partial Approval | MICHEL ABAJAN |
| Sewer | 12/9/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/3/2023 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2023 | Partial Approval | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 1/3/2023 | Corrections Issued | JAVIER RAMOS JR |
| Underground Mechanical | 1/3/2023 | Partial Approval | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 1/4/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 1/10/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 1/10/2023 | Approved | JAVIER RAMOS JR |
| Gas Test | 1/10/2023 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 1/10/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Insulation | 1/10/2023 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 1/10/2023 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/10/2023 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 1/17/2023 | Conditional Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2023 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 1/17/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/24/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 1/24/2023 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 1/24/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 3/7/2023 | Approved | JAVIER RAMOS JR |
| Final | 3/7/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 3/7/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 3/7/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Final | 3/7/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 3/7/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 3/7/2023 | Approved | JAVIER RAMOS JR |
| Final | 3/15/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Gas Test | 3/15/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 3/15/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 3/15/2023 | Approved | JAVIER RAMOS JR |