CONVERT EX ATTACHED 20'-0" X 20'-0" GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (e). ALL WORK PER WFPP.
Permit Issued
Issued on 12/15/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2022 APPLICANT
Assigned to Plan Check Engineer 8/26/2022 HAYATO TSUCHIYA
Corrections Issued 8/27/2022 HAYATO TSUCHIYA
Building Plans Picked Up 8/31/2022 APPLICANT
Applicant returned to address corrections 12/13/2022 LUIS RINCON
Plan Check Approved 12/15/2022 MIROOSH KHACHATOORIAN
Issued 12/15/2022 APPLICANT
CofO in Progress 10/17/2024 JENNIFER RABUCHIN
CofO Issued 10/29/2024 DANIEL ORRANTE
Permit Finaled 10/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/29/2022 MEGAN GODINEZ
Sewer availability Cleared 8/29/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/30/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 8/30/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 8/30/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 8/30/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/18/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 5/22/2023 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 5/22/2023 Approved JENNIFER RABUCHIN
Underground Mechanical 5/22/2023 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/8/2023 Not Ready for Inspection ROBERT GOLD
Green Building Rough 6/8/2023 Not Ready for Inspection ROBERT GOLD
MERV13>=Rough 6/8/2023 Not Ready for Inspection ROBERT GOLD
METHANE-Rough 6/8/2023 Approved ROBERT GOLD
PLUMBING-Rough 6/8/2023 Corrections Issued ROBERT GOLD
BUILDING-Rough-Frame 6/22/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 6/22/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 6/22/2023 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 6/22/2023 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 6/22/2023 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 6/30/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 6/30/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/7/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 7/7/2023 Approved JENNIFER RABUCHIN
Green Building Rough 7/7/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 7/7/2023 Approved JENNIFER RABUCHIN
Insulation 7/7/2023 Approved JENNIFER RABUCHIN
MERV13>=Rough 7/7/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/7/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 7/26/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/26/2023 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 9/18/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/9/2024 Approved JENNIFER RABUCHIN
Final 10/9/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/9/2024 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 10/9/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/9/2024 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 10/9/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/15/2024 Approved JENNIFER RABUCHIN
Final 10/15/2024 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 10/15/2024 Approved JENNIFER RABUCHIN
HVAC-Final 10/15/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/15/2024 Approved JENNIFER RABUCHIN