12357-12361 N JOLETTE AVE 91344
Certificate Information: 12357-12361 N JOLETTE AVE 91344
- Application / Permit
- 22016-20000-24624
- Plan Check / Job No.
- B22VN12502
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE INTO A (N) 22'-6" x 21'-6" JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code65852.2(e)(1)(A) and 65852.229. ALL WORK PER WFPP. SEE COMMENTS
- Permit Issued
- Issued on 12/6/2022
- Issuing Office
- Current Status
- CofO Issued on 6/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2022 | ROSENDO MEDINA |
| Corrections Issued | 8/19/2022 | ROSENDO MEDINA |
| Applicant returned to address corrections | 11/17/2022 | ALFRED RAMIREZ |
| Plan Check Approved | 12/1/2022 | SARKIS HARABEDIAN |
| Issued | 12/6/2022 | APPLICANT |
| CofO in Progress | 6/8/2023 | STEVEN BACK |
| Permit Finaled | 6/13/2023 | JOHN JANSON |
| CofO Issued | 6/13/2023 | JOHN JANSON |
| Permit Finaled | 6/13/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 8/23/2022 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 9/1/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Markarian Setrag; Lic. No.: 832632-B | , |
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/9/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 2/9/2023 | Approved | SEAN HAUPT |
| Special/Order Compliance | 2/9/2023 | Corrections Issued | SEAN HAUPT |
| Underground Mechanical | 2/9/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 2/28/2023 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 2/28/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Rough | 2/28/2023 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 2/28/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 2/28/2023 | Not Ready for Inspection | SEAN HAUPT |
| Special/Order Compliance | 2/28/2023 | Partial Inspection | JUSTIN HAWLEY |
| Verify Sprinkler Sign Off | 2/28/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 3/9/2023 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 3/9/2023 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Approved | STEVEN BACK |
| PLUMBING-Rough | 3/9/2023 | Approved | STEVEN BACK |
| Sewer | 3/9/2023 | Approved | STEVEN BACK |
| Green Building Rough | 3/14/2023 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 3/14/2023 | Partial Approval | STEVEN BACK |
| Shower Pan | 3/14/2023 | Approved | STEVEN BACK |
| Insulation | 3/16/2023 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 3/16/2023 | Approved | MORRIS JACKSON |
| Drywall Nailing | 3/21/2023 | Approved | SEAN HAUPT |
| Drywall Nailing | 3/23/2023 | No Access for Inspection | STEVEN BACK |
| Final | 5/31/2023 | Corrections Issued | STEVEN BACK |
| Green Building Final | 5/31/2023 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 5/31/2023 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 5/31/2023 | Approved | STEVEN BACK |
| Final | 6/8/2023 | OK to Issue CofO | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/8/2023 | SGSOV Approved | STEVEN BACK |