2514-2516 N ROSCOMARE ROAD 90077
Certificate Information: 2514-2516 N ROSCOMARE ROAD 90077
- Application / Permit
- 22016-20000-24542
- Plan Check / Job No.
- B22VN12468
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED BASEMENT REC ROOM INTO ACCESSORY DWELLING UNIT ( 965 SF ) PER CA GOV. STATE CODE 65852.2(e)(1)(A).
- Permit Issued
- Issued on 1/10/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2022 | ROSENDO MEDINA |
| Corrections Issued | 8/23/2022 | ROSENDO MEDINA |
| Building Plans Picked Up | 8/30/2022 | APPLICANT |
| Plan Check Approved | 1/4/2023 | ALEC MOUSAKHANIAN |
| Issued | 1/10/2023 | APPLICANT |
| CofO in Progress | 8/3/2024 | CHRISTOPHER WILSON |
| Permit Finaled | 8/7/2024 | DANIEL ORRANTE |
| CofO Issued | 8/7/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/7/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 10/11/2022 | RYAN LY |
| Address approval | Cleared | 10/12/2022 | AHMED AMARRAGY |
| Sewer availability | Cleared | 10/12/2022 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2022 | AHMED AMARRAGY |
| Specific Plan | Cleared | 12/27/2022 | OLGA AYALA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/29/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Inspection | 11/27/2023 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 3/14/2024 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 4/23/2024 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 5/21/2024 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 6/10/2024 | Approved | CHRISTOPHER WILSON |
| Final | 6/10/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 6/10/2024 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Service/Power Release | 6/10/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Smoke Detectors | 6/10/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Service/Power Release | 6/21/2024 | Approved | CHRISTOPHER WILSON |
| Service/Power Release | 7/2/2024 | Approved | CHRISTOPHER WILSON |
| Service/Power Release | 7/10/2024 | Approved | CHRISTOPHER WILSON |
| Final | 8/2/2024 | OK to Issue CofO | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 8/2/2024 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 8/2/2024 | Approved | CHRISTOPHER WILSON |