857 1/2 E 77TH ST 90001
Certificate Information: 857 1/2 E 77TH ST 90001
- Application / Permit
- 22016-20000-24178
- Plan Check / Job No.
- B22VN12368
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 19'-9" X 31'-3" DETACHED 3-CAR GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 11/22/2022
- Issuing Office
- Current Status
- CofO Issued on 1/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 8/16/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 10/28/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 11/15/2022 | JEROME MAGAT PALMA |
| Issued | 11/22/2022 | APPLICANT |
| CofO in Progress | 1/10/2024 | MICHAEL LEWIS |
| Permit Finaled | 1/13/2024 | DEROLD HAUFF |
| CofO Issued | 1/13/2024 | DEROLD HAUFF |
| Permit Finaled | 1/13/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 8/19/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 8/20/2022 | CHRISTOPHER ROCHA |
| Construction near power lines | Cleared | 10/17/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/1/2023 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 8/4/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 8/4/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 8/4/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 8/29/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 8/29/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 8/29/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/30/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 8/30/2023 | Approved | MICHAEL LEWIS |
| Insulation | 9/5/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 9/5/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 9/5/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 9/12/2023 | Approved | MICHAEL LEWIS |
| Insulation | 9/12/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 9/12/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 9/18/2023 | Approved | MICHAEL LEWIS |
| Final | 12/29/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 12/29/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 12/29/2023 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 12/29/2023 | Approved | MICHAEL LEWIS |
| Final | 1/9/2024 | OK to Issue CofO | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Approved | MICHAEL LEWIS |