8217 S BARNSLEY AVE 90045
Certificate Information: 8217 S BARNSLEY AVE 90045
- Application / Permit
- 22016-20000-23870
- Plan Check / Job No.
- B22VN12229
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX. DETACHED GARAGE/STORAGE INTO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). WORK PER WFPP AND ENGINEER DETAIL.
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 8/17/2022 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 8/18/2022 | APPLICANT |
| Applicant returned to address corrections | 8/24/2022 | JESSE ARELLANO |
| Plan Check Approved | 8/25/2022 | ROSENDO MEDINA |
| No Progress | 8/25/2022 | ROSENDO MEDINA |
| Plan Check Approved | 8/25/2022 | ROSENDO MEDINA |
| Issued | 8/25/2022 | APPLICANT |
| CofO in Progress | 4/17/2023 | BOBBY KEY |
| Permit Finaled | 4/18/2023 | DANIEL ORRANTE |
| CofO Issued | 4/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2022 | CATHERINE ADROVER |
| Grading Pre-Inspection | Cleared | 8/23/2022 | MANUEL TEJADA |
| Sewer availability | Cleared | 8/23/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2022 | CATHERINE ADROVER |
| Specific Plan | Cleared | 8/25/2022 | DANG NGUYEN |
Contact Information
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | 21204 VANOWEN STREET CANOGA PARK, CA 91303 |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/11/2022 | Partial Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 11/2/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 11/2/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 11/9/2022 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 11/15/2022 | Approved | BOBBY KEY |
| Sewer | 11/15/2022 | Approved | BOBBY KEY |
| Underground Mechanical | 11/15/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 11/28/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 12/23/2022 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 12/23/2022 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2022 | Partial Approval | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 12/29/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 1/5/2023 | Approved | HERBERT GIRON |
| HVAC-Rough | 1/5/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 1/5/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 1/11/2023 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 1/11/2023 | Approved | HERBERT GIRON |
| Insulation | 1/17/2023 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 1/17/2023 | Partial Approval | BOBBY KEY |
| Shower Pan | 1/17/2023 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 1/30/2023 | Partial Approval | HERBERT GIRON |
| Insulation | 1/30/2023 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/8/2023 | Approved | BOBBY KEY |
| Green Building Rough | 2/8/2023 | Approved | BOBBY KEY |
| Insulation | 2/8/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 2/8/2023 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 2/13/2023 | Approved | BOBBY KEY |
| Shower Pan | 2/13/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 2/17/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/30/2023 | SGSOV Not Ready | HERBERT GIRON |
| ELECTRICAL-Final | 4/5/2023 | Corrections Issued | BOBBY KEY |
| Final | 4/5/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 4/5/2023 | Approved | BOBBY KEY |
| HVAC-Final | 4/5/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 4/5/2023 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 4/5/2023 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 4/12/2023 | Corrections Issued | BOBBY KEY |
| Final | 4/12/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 4/12/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 4/12/2023 | Approved | BOBBY KEY |
| Smoke Detectors | 4/12/2023 | Approved | BOBBY KEY |
| Final | 4/17/2023 | OK to Issue CofO | BOBBY KEY |