11831 W OTSEGO ST 91607

Certificate Information: 11831 W OTSEGO ST 91607

Application / Permit
22016-20000-23865
Plan Check / Job No.
B22VN12227
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERSION OF AN EXISTING 19'x20' GARAGE TO AN ADU PER GCS65852.2(e)(1)(A)
Permit Issued
Issued on 1/21/2023
Issuing Office
Current Status
CofO Issued on 7/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/10/2022 JOSEPH RAFOLS
Corrections Issued 8/11/2022 JOSEPH RAFOLS
Applicant returned to address corrections 8/18/2022 MINA HABILI
Plan Check Approved 9/7/2022 JOSEPH RAFOLS
Issued 1/21/2023 APPLICANT
CofO in Progress 6/3/2026 JAVIER RAMOS JR
Permit Finaled 7/21/2026 DANIEL ORRANTE
CofO Issued 7/21/2026 DANIEL ORRANTE
Permit Finaled 7/21/2026 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/17/2022 MEGAN GODINEZ
Sewer availability Cleared 8/17/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/18/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 8/18/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 8/18/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 8/18/2022 MEGAN GODINEZ
Specific Plan Cleared 8/23/2022 CORREY KITCHENS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/10/2025 Approved JAVIER RAMOS JR
Sewer 7/10/2025 Approved JAVIER RAMOS JR
Underground Mechanical 7/10/2025 Partial Approval JAVIER RAMOS JR
Drywall Nailing 11/5/2025 Approved JAVIER RAMOS JR
Insulation 11/5/2025 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 11/5/2025 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 4/30/2026 Approved JAVIER RAMOS JR
ELECTRICAL-Final 4/30/2026 Corrections Issued JAVIER RAMOS JR
Final 4/30/2026 Corrections Issued JAVIER RAMOS JR
Green Building Final 4/30/2026 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 4/30/2026 Approved JAVIER RAMOS JR
HVAC-Final 4/30/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 4/30/2026 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/30/2026 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 4/30/2026 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/19/2026 Approved JAVIER RAMOS JR
Final 5/19/2026 Corrections Issued JAVIER RAMOS JR
Green Building Final 5/19/2026 Partial Inspection JAVIER RAMOS JR
PLUMBING-Final 5/19/2026 Approved JAVIER RAMOS JR
Final 6/3/2026 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 6/3/2026 Approved JAVIER RAMOS JR