9580 N LEV AVE 91331

Certificate Information: 9580 N LEV AVE 91331

Application / Permit
22016-20000-23790
Plan Check / Job No.
B22VN12198
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-6" X 20' DEATCHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 11/17/2022
Issuing Office
Current Status
CofO Issued on 5/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/16/2022 JEFFREY TANGONAN
Corrections Issued 8/18/2022 OMAR GARNICA
Building Plans Picked Up 8/19/2022 APPLICANT
Plan Check Approved 11/17/2022 MIROOSH KHACHATOORIAN
Issued 11/17/2022 APPLICANT
CofO in Progress 5/25/2023 MICHEL ABAJAN
CofO Issued 5/26/2023 MICHAEL SMITH
Permit Finaled 5/26/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/19/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 8/19/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 10/17/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 10/17/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 11/15/2022 TINA MIRANDA

Contact Information

Contractor Ramirez Construction Co; Lic. No.: 1023300-B 2636 PINE PL      SOUTH GATE, CA 90280

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/19/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 1/19/2023 Partial Approval MICHEL ABAJAN
Sewer 1/19/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/27/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 1/27/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 1/27/2023 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 1/27/2023 Approved JENNIFER RABUCHIN
MERV13>=Rough 1/27/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 1/27/2023 Approved JENNIFER RABUCHIN
Insulation 1/31/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/31/2023 Approved MICHEL ABAJAN
Drywall Nailing 2/3/2023 Approved MICHEL ABAJAN
Green Building Rough 2/3/2023 Approved MICHEL ABAJAN
Shower Pan 2/3/2023 Corrections Issued MICHEL ABAJAN
MERV13>=Final 2/7/2023 Approved MICHEL ABAJAN
Shower Pan 2/7/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/13/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/22/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/22/2023 Corrections Issued JENNIFER RABUCHIN
Final 5/22/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 5/22/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/22/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 5/22/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 5/25/2023 Approved MICHEL ABAJAN
Final 5/25/2023 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 5/25/2023 Approved MICHEL ABAJAN
PLUMBING-Final 5/25/2023 Approved MICHEL ABAJAN
Service/Power Release 5/25/2023 Approved MICHEL ABAJAN
Smoke Detectors 5/25/2023 Approved MICHEL ABAJAN