5639 N NORWICH AVE 91411

Certificate Information: 5639 N NORWICH AVE 91411

Application / Permit
22016-20000-23766
Plan Check / Job No.
B22VN12186
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A)
Permit Issued
Issued on 9/14/2022
Issuing Office
Valley
Current Status
CofO Issued on 6/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/15/2022 PINANK PATEL
Corrections Issued 8/15/2022 PINANK PATEL
Building Plans Picked Up 8/22/2022 APPLICANT
Plan Check Approved 9/12/2022 YAQUB MIRZA
Issued 9/14/2022 APPLICANT
CofO in Progress 6/22/2023 RYAN SALAZAR
Permit Finaled 6/27/2023 MICHAEL SMITH
CofO Issued 6/27/2023 MICHAEL SMITH
Permit Finaled 6/27/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/24/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/24/2022 MEGAN GODINEZ
Sewer availability Cleared 8/24/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 8/24/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 8/24/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 8/24/2022 MEGAN GODINEZ
Construction near power lines Cleared 9/14/2022 JOHN BACON

Contact Information

Contractor Owner-Builder       ,
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/11/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 1/11/2023 Corrections Issued RYAN SALAZAR
Gas Test 1/11/2023 Approved RYAN SALAZAR
PLUMBING-Rough 1/11/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 1/27/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 3/1/2023 Approved JENNIFER RABUCHIN
Green Building Rough 3/1/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 3/1/2023 Corrections Issued JENNIFER RABUCHIN
Insulation 3/1/2023 Partial Approval JENNIFER RABUCHIN
Wood Frame 3/1/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 3/2/2023 Approved RYAN SALAZAR
Insulation 3/2/2023 Approved RYAN SALAZAR
Pre-Inspection 3/2/2023 Partial Inspection RYAN SALAZAR
Wood Frame 3/2/2023 Approved RYAN SALAZAR
Drywall Nailing 3/16/2023 Approved CHRISTOPHER DELLEFIELD
Shower Pan 3/16/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/7/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 6/20/2023 Approved RYAN SALAZAR
Final 6/20/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 6/20/2023 Approved RYAN SALAZAR
Green Building Rough 6/20/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 6/20/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 6/20/2023 Approved RYAN SALAZAR