22674-22676 W HAMLIN ST 91307

Certificate Information: 22674-22676 W HAMLIN ST 91307

Application / Permit
22016-20000-23635
Plan Check / Job No.
B22VN12113
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ATT GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 8/15/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2022 APPLICANT
Assigned to Plan Check Engineer 8/9/2022 LUISANGEL VALENZUELA
Corrections Issued 8/9/2022 LUISANGEL VALENZUELA
Building Plans Picked Up 8/11/2022 APPLICANT
Plan Check Approved 8/15/2022 PINANK PATEL
Issued 8/15/2022 APPLICANT
CofO in Progress 2/27/2023 TROY SANDERS
CofO Issued 2/27/2023 JOHN JANSON
Permit Finaled 2/27/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/11/2022 ROMAN GUTIERREZ
Sewer availability Cleared 8/11/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/12/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/9/2022 Approved TROY SANDERS
PLUMBING-Rough 9/9/2022 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 9/23/2022 Approved TROY SANDERS
ELECTRICAL-Rough 9/23/2022 Approved TROY SANDERS
Gas Test 9/23/2022 Approved TROY SANDERS
Green Building Rough 9/23/2022 Not Ready for Inspection TROY SANDERS
HVAC-Rough 9/23/2022 Approved TROY SANDERS
PLUMBING-Rough 9/23/2022 Approved TROY SANDERS
Insulation 10/12/2022 Approved TROY SANDERS
Interior/Exterior Lathing 10/12/2022 Approved TROY SANDERS
Shower Pan 10/12/2022 Approved TROY SANDERS
Drywall Nailing 10/19/2022 Approved TROY SANDERS
Green Building Rough 10/19/2022 Approved TROY SANDERS
Final 2/13/2023 Corrections Issued TROY SANDERS
Green Building Final 2/13/2023 Not Ready for Inspection TROY SANDERS
SGSOV-Seismic Gas S/O Valve 2/13/2023 SGSOV Approved TROY SANDERS
Smoke Detectors 2/13/2023 Approved TROY SANDERS
Final 2/27/2023 OK to Issue CofO TROY SANDERS