13812-13814 N SIMSHAW AVE 91342

Certificate Information: 13812-13814 N SIMSHAW AVE 91342

Application / Permit
22016-20000-23627
Plan Check / Job No.
B22VN12099
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 21' X 21' ATTACHED GARAGE TO AN ATTACHED ACCESSORY DWELLING UNIT PER GCS 65852.2. (e) (1) (A).
Permit Issued
Issued on 9/14/2022
Issuing Office
Current Status
CofO Issued on 6/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/15/2022 ALEC MOUSAKHANIAN
Corrections Issued 8/16/2022 ALEC MOUSAKHANIAN
Plan Check Approved 9/14/2022 ALEC MOUSAKHANIAN
Issued 9/14/2022 APPLICANT
CofO in Progress 5/24/2023 ARAM AVEDISIAN
CofO Issued 6/5/2023 MICHAEL SMITH
Permit Finaled 6/5/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/18/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 8/18/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 8/18/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 8/18/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 8/18/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 8/18/2022 JOSE DUARTE-DIAZ
Grading Pre-Inspection Cleared 8/24/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/26/2022 No Result Entered KENNETH KUROWSKI
Footing/Foundation/Slab 10/27/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 10/27/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 12/12/2022 Approved MICHEL ABAJAN
HVAC-Rough 12/12/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 12/12/2022 Approved MICHEL ABAJAN
Wood Frame 12/21/2022 Partial Approval ARAM AVEDISIAN
Insulation 12/28/2022 Conditional Approval ARAM AVEDISIAN
Interior/Exterior Lathing 12/28/2022 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/5/2023 Approved ARAM AVEDISIAN
Drywall Nailing 1/31/2023 Approved ARAM AVEDISIAN
Shower Pan 1/31/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 2/15/2023 Approved MICHEL ABAJAN
Pre-Inspection 2/15/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 5/5/2023 No Access for Inspection ARAM AVEDISIAN
Final 5/5/2023 No Access for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 5/5/2023 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 5/5/2023 No Access for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 5/10/2023 Approved ARAM AVEDISIAN
Final 5/10/2023 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 5/10/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 5/10/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 5/24/2023 Approved ARAM AVEDISIAN
Final 5/24/2023 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 5/24/2023 Approved ARAM AVEDISIAN
PLUMBING-Final 5/24/2023 Approved ARAM AVEDISIAN