8425 N RESEDA BLVD 91324
Certificate Information: 8425 N RESEDA BLVD 91324
- Application / Permit
- 22016-20000-23594
- Plan Check / Job No.
- B22VN12090
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- ePlan: EXTERIOR REMODEL AND TENANT IMPROVEMENT TO (E) RESTAURANT & RETAIL
- Permit Issued
- Issued on 6/14/2023
- Issuing Office
- Current Status
- Issued on 6/14/2023
Permit Application Status History
| Submitted | 8/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2022 | DANIEL YIP |
| Corrections Issued | 8/16/2022 | DANIEL YIP |
| Quality Review Completed | 8/17/2022 | GARO TELMI |
| Applicant returned to address corrections | 11/23/2022 | DANIEL YIP |
| Applicant returned to address corrections | 1/12/2023 | DANIEL YIP |
| Applicant returned to address corrections | 3/2/2023 | DANIEL YIP |
| Applicant returned to address corrections | 3/23/2023 | DANIEL YIP |
| Applicant returned to address corrections | 3/31/2023 | DANIEL YIP |
| Plan Check Approved | 5/19/2023 | DANIEL YIP |
| Issued | 6/14/2023 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 3/1/2023 | AARON COSTA |
| Food establishment approval | Cleared | 3/23/2023 | LACDHS APPROVED |
| DAS Clearance | Cleared | 5/3/2023 | Hernan Arreola |
Contact Information
| Architect | Klimko,, Gregory C; Lic. No.: C33391 | 3611 SUNRISE BAY POINTE LITTLE ELM, TX 75068 |
| Architect | Klimko,, Gregory C; Lic. No.: NA33391 | , |
| Contractor | Parkway C & A Lp; Lic. No.: 1023585-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/8/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 8/10/2023 | No Access for Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 8/13/2023 | Corrections Issued | DANNY RODRIGUEZ |
| Insulation | 8/16/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 8/16/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 8/18/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 8/25/2023 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 9/1/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 9/6/2023 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 9/12/2023 | Off-Hour Fees Due | |
| Drywall Nailing | 9/12/2023 | Partial Approval | JEFFREY DURAN |
| Final | 9/12/2023 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 9/12/2023 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 9/12/2023 | Partial Approval | JEFFREY DURAN |
| Green Building Final | 9/12/2023 | Off-Hour Fees Due | |
| Green Building Rough | 9/12/2023 | Off-Hour Fees Due | |
| Green Building Rough | 9/12/2023 | Partial Approval | JEFFREY DURAN |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | Off-Hour Fees Due | |
| Smoke Detectors | 9/12/2023 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 9/26/2023 | SGSOV Approved | DEANDRE HOFFMAN |
| Green Building Rough | 10/2/2023 | Approved | DEANDRE HOFFMAN |