23211 W VANOWEN ST 1-3 91307
Certificate Information: 23211 W VANOWEN ST 1-3 91307
- Application / Permit
- 22016-20000-23540
- Plan Check / Job No.
- B22VN12071
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF THE (E) S.F.D. TO A (N) 20'-0" x 20-0" JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22
- Permit Issued
- Issued on 9/28/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2022 | ALFRED RAMIREZ |
| Corrections Issued | 8/9/2022 | ALFRED RAMIREZ |
| Building Plans Picked Up | 8/11/2022 | APPLICANT |
| Applicant returned to address corrections | 9/16/2022 | DANIEL ABRAMYAN |
| Plan Check Approved | 9/28/2022 | ALEC MOUSAKHANIAN |
| Issued | 9/28/2022 | APPLICANT |
| CofO in Progress | 4/11/2024 | TROY SANDERS |
| Permit Finaled | 4/30/2025 | JOHN JANSON |
| CofO Issued | 4/30/2025 | JOHN JANSON |
| Permit Finaled | 4/30/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/18/2022 | ROMAN GUTIERREZ |
| Miscellaneous | Cleared | 8/22/2022 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/16/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 3/3/2023 | Approved | TROY SANDERS |
| Insulation | 3/3/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 6/16/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 6/16/2023 | Corrections Issued | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 6/16/2023 | SGSOV Approved | JUSTIN HAWLEY |
| Smoke Detectors | 6/16/2023 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 7/20/2023 | Approved | TROY SANDERS |
| Final | 7/20/2023 | Corrections Issued | TROY SANDERS |
| Green Building Final | 7/20/2023 | Approved | TROY SANDERS |
| Final | 4/11/2024 | OK to Issue CofO | TROY SANDERS |