22648 W DOLOROSA ST 91367
Certificate Information: 22648 W DOLOROSA ST 91367
- Application / Permit
- 22016-20000-23416
- Plan Check / Job No.
- B22VN11991
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-2" X 20'-3" REC. ROOM PORTION OF BLDG. INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(A). ATTACHED CARPORT TO REMAIN.
- Permit Issued
- Issued on 9/1/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | ALEC MOUSAKHANIAN |
| Corrections Issued | 8/4/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 9/1/2022 | LAWRENCE QUIRANTE |
| Issued | 9/1/2022 | APPLICANT |
| CofO in Progress | 4/4/2024 | TROY SANDERS |
| Permit Finaled | 5/2/2024 | JOHN JANSON |
| CofO Issued | 5/2/2024 | JOHN JANSON |
| Permit Finaled | 5/2/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 8/10/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 8/10/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/13/2023 | Approved | TROY SANDERS |
| Pre-Inspection | 7/24/2023 | Approved | TROY SANDERS |
| Wood Frame | 10/12/2023 | Not Ready for Inspection | TROY SANDERS |
| Deputy Drilled-In Anchors | 10/19/2023 | Partial Approval | TROY SANDERS |
| Deputy Drilled-In Anchors | 10/27/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 11/16/2023 | Approved | TROY SANDERS |
| Green Building Rough | 11/16/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 12/13/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/3/2024 | Partial Approval | TROY SANDERS |
| Final | 4/3/2024 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 4/3/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 4/3/2024 | Approved | TROY SANDERS |