13831 W ROSCOE BLVD 91402

Certificate Information: 13831 W ROSCOE BLVD 91402

Application / Permit
22016-20000-23399
Plan Check / Job No.
B22VN11984
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 9/24/2022
Issuing Office
Current Status
CofO in Progress on 9/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/4/2022 APPLICANT
Assigned to Plan Check Engineer 8/12/2022 DANIEL YIP
Corrections Issued 8/15/2022 DANIEL YIP
Plan Check Approved 9/7/2022 DANIEL YIP
Issued 9/24/2022 APPLICANT
CofO in Progress 9/12/2025 VINCENT HANLEY
CofO in Progress 9/12/2025 VINCENT HANLEY
CofO in Progress 9/12/2025 VINCENT HANLEY
CofO in Progress 9/12/2025 VINCENT HANLEY
CofO in Progress 9/12/2025 JUAN VALENZUELA
CofO in Progress 9/12/2025 JUAN VALENZUELA

Permit Application Clearance Information

Address approval Cleared 8/22/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/22/2022 MEGAN GODINEZ
Sewer availability Cleared 8/22/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 8/22/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 8/22/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 8/22/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/14/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Pre-Inspection 3/16/2023 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 4/10/2023 SGSOV Not Ready GREGG CUMMINGS
Sewer 4/10/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 4/17/2023 Partial Approval CHRISTOPHER DELLEFIELD
Sewer 4/21/2023 Approved GREGG CUMMINGS
Underground Mechanical 4/21/2023 Approved GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 6/5/2023 No Access for Inspection CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 6/5/2023 No Access for Inspection CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 6/9/2023 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 6/9/2023 Not Ready for Inspection GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 6/21/2023 Approved GREGG CUMMINGS
Footing/Foundation/Slab 6/21/2023 Approved GREGG CUMMINGS
Gas Test 8/3/2023 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 8/3/2023 SGSOV Not Ready GREGG CUMMINGS
Wood Frame 8/3/2023 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 8/29/2023 Corrections Issued GREGG CUMMINGS
HVAC-Rough 8/29/2023 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 8/29/2023 Approved GREGG CUMMINGS
ELECTRICAL-Rough 9/5/2023 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 9/5/2023 Approved CHRISTOPHER ROJAS
Shower Pan 9/5/2023 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/22/2023 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 9/26/2023 Approved GREGG CUMMINGS
ELECTRICAL-Rough 9/26/2023 Approved GREGG CUMMINGS
Insulation 9/26/2023 Approved GREGG CUMMINGS
Drywall Nailing 10/12/2023 Approved GREGG CUMMINGS
Underground Mechanical 10/17/2023 Partial Approval GREGG CUMMINGS
ELECTRICAL-Final 9/12/2025 Approved VINCENT HANLEY
Final 9/12/2025 Corrections Issued VINCENT HANLEY
Final 9/12/2025 Not Ready for Inspection VINCENT HANLEY
HVAC-Final 9/12/2025 Approved VINCENT HANLEY
PLUMBING-Final 9/12/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Approved VINCENT HANLEY
Service/Power Release 9/12/2025 Approved VINCENT HANLEY
Smoke Detectors 9/12/2025 Approved VINCENT HANLEY
Final 9/15/2025 Corrections Issued VINCENT HANLEY