17300 W VANOWEN ST 91406
Certificate Information: 17300 W VANOWEN ST 91406
- Application / Permit
- 22016-20000-23316
- Plan Check / Job No.
- B22VN11945
- Group
- Building
- Type
- Nonbldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (61) Open Parking Lot
- Work Description
- ePLAN. PARKING LOT RESTRIPE FOR ELECTRIC VEHICLE CHARGING. NEW BICYCLE PARKING. NEW CONCRETE PADS FOR EQUIPMENT.
- Permit Issued
- Issued on 1/11/2024
- Issuing Office
- Current Status
- CofO Issued on 1/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2022 | KEVIN MORALES |
| Corrections Issued | 9/6/2022 | KEVIN MORALES |
| Quality Review Completed | 9/7/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 1/30/2023 | KEVIN MORALES |
| Applicant returned to address corrections | 3/23/2023 | KEVIN MORALES |
| Plan Check Approved | 4/6/2023 | KEVIN MORALES |
| No Progress | 1/2/2024 | KEVIN MORALES |
| Plan Check Approved | 1/2/2024 | KEVIN MORALES |
| Issued | 1/11/2024 | APPLICANT |
| CofO in Progress | 1/27/2025 | ROBERT DAVIS |
| Permit Finaled | 1/28/2025 | JEFFREY DURAN |
| CofO Issued | 1/28/2025 | JEFFREY DURAN |
| Permit Finaled | 1/28/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| ZI | Cleared | 11/8/2022 | DANG NGUYEN |
| DAS Clearance | Cleared | 3/15/2023 | Hernan Arreola |
Contact Information
| Architect | Maresca,, Christopher Thomas; Lic. No.: C32449 | 2204 ALBATROSS ST SAN DIEGO, CA 92101 |
| Contractor | Horizon Underground Inc; Lic. No.: 802076-A | 1595 MOUNTAIN AVE NORCO, CA 92860 |
| Engineer | Kim,, Yoo Jin; Lic. No.: S5771 | 129 GERBERA STREET DANVILLE, CA 94506 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/21/2024 | Conditional Approval | STEVEN LEVITT |
| Rough | 2/22/2024 | Partial Inspection | STEVEN LEVITT |
| Rough | 2/23/2024 | Partial Inspection | STEVEN LEVITT |
| Excavation/Setback/Form/Re-Bar | 3/1/2024 | Not Ready for Inspection | STEVEN LEVITT |
| Footing/Foundation/Slab | 3/29/2024 | Approved | STEVEN LEVITT |
| Final | 6/24/2024 | Corrections Issued | DEANDRE HOFFMAN |
| Final | 1/9/2025 | OK to Issue CofO | ROBERT DAVIS |