8640 N VAN NUYS BLVD 91402
Certificate Information: 8640 N VAN NUYS BLVD 91402
- Application / Permit
- 22016-20000-23314
- Plan Check / Job No.
- B22VN11944
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Clinic
- Work Description
- ePlan TENANT IMPROVEMENTS: 7'5"X 8'10"ELEVATOR LOBBY AND 11'7" X 4'10" $ 4'6" X 8'8" INFILL STAIRS 2ND FLOOR ADDITIONS & CHANGE OF USE AND REMODEL FROM (E) 128'6" X 106'9"'(12,111 SQ.FT.) IRREGULAR SHAPED GROCERY MARKET TO MEDICAL OSHPD CLINIC , REPLACE ROOFTOP HVAC UNITS WITH NEW (8) UNITS (830 LBS EACH) , NFPA 13 FIRE SPRINKLER THROUGHOUT THE BUILDING , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 7/12/2023
- Issuing Office
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | RARES BODEA |
| Corrections Issued | 9/3/2022 | RARES BODEA |
| Quality Review Completed | 9/8/2022 | STEVEN KIM |
| Applicant returned to address corrections | 12/20/2022 | RARES BODEA |
| Applicant returned to address corrections | 12/23/2022 | RARES BODEA |
| Applicant returned to address corrections | 1/24/2023 | RARES BODEA |
| Applicant returned to address corrections | 2/1/2023 | RARES BODEA |
| Applicant returned to address corrections | 2/17/2023 | RARES BODEA |
| Plan Check Approved | 2/25/2023 | RARES BODEA |
| Issued | 7/12/2023 | APPLICANT |
| CofO in Progress | 8/7/2024 | ANDREW DORSO |
| Permit Finaled | 8/7/2024 | JEFFREY DURAN |
| CofO Issued | 8/7/2024 | JEFFREY DURAN |
| Permit Finaled | 8/7/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/8/2022 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 9/12/2022 | RUBEN VASQUEZ |
| "Q" conditions | Cleared | 12/8/2022 | PEGGY MALONE-BROWN |
| Supp. Use District POD/CDO/TDO | Cleared | 12/8/2022 | PEGGY MALONE-BROWN |
| ZI | Cleared | 12/8/2022 | PEGGY MALONE-BROWN |
| Green Code | Cleared | 12/28/2022 | Hernan Arreola |
| DAS Clearance | Cleared | 1/9/2023 | Hernan Arreola |
Contact Information
| Architect | Birba,, Pedro Perfecto; Lic. No.: C12848 | 2350 HYPERION AVENUE LOS ANGELES, CA 90027 |
| Contractor | Parker Brown Inc; Lic. No.: 689613-B | , |
| Engineer | Schulz,, Les Eric; Lic. No.: S2570 | 346 N LIMA SIERRA MADRE, CA 91024 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/10/2023 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 10/13/2023 | Partial Approval | DANNY RODRIGUEZ |
| Reinforced Concrete Frame | 10/13/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Partial Inspection | CAMERON CHABAN |
| Green Building Rough | 11/3/2023 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 11/3/2023 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 11/13/2023 | Partial Inspection | ANDREW DORSO |
| Green Building Rough | 11/22/2023 | Approved | ANDREW DORSO |
| Wood Frame | 11/22/2023 | Partial Inspection | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Partial Inspection | ANDREW DORSO |
| Reinforced Concrete Frame | 11/27/2023 | Partial Inspection | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2024 | Not Ready for Inspection | ANDREW DORSO |
| Reinforced Concrete Frame | 1/5/2024 | Corrections Issued | ANDREW DORSO |
| Wood Frame | 1/24/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 1/26/2024 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Concrete | 2/2/2024 | Approved | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 2/2/2024 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 2/7/2024 | Partial Inspection | ANDREW DORSO |
| Special/Order Compliance | 2/7/2024 | Partial Inspection | MELVIN GIRTON |
| Insulation | 2/8/2024 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 2/8/2024 | Partial Inspection | ANDREW DORSO |
| Special/Order Compliance | 2/8/2024 | Partial Inspection | MELVIN GIRTON |
| Light Gage Steel Frame | 2/20/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 2/21/2024 | Partial Inspection | ANDREW DORSO |
| Insulation | 2/21/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 2/23/2024 | Partial Inspection | ANDREW DORSO |
| Insulation | 2/23/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 2/28/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 3/5/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 3/7/2024 | Not Ready for Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 3/7/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 3/27/2024 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 4/4/2024 | Partial Inspection | ANDREW DORSO |
| T-Bar Ceiling | 4/10/2024 | Not Ready for Inspection | ANDREW DORSO |
| T-Bar Ceiling | 4/12/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 4/17/2024 | Partial Inspection | ANDREW DORSO |
| T-Bar Ceiling | 4/24/2024 | Not Ready for Inspection | ANDREW DORSO |
| T-Bar Ceiling | 4/25/2024 | Partial Inspection | ANDREW DORSO |
| T-Bar Ceiling | 5/8/2024 | Approved | GREGORY POMISH |
| Interior/Exterior Lathing | 5/13/2024 | Approved | ANDREW DORSO |
| Final | 7/10/2024 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 7/10/2024 | Approved | ANDREW DORSO |
| Green Building Final | 7/10/2024 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 7/10/2024 | Not Ready for Inspection | ANDREW DORSO |
| Wood Frame | 7/10/2024 | Approved | ANDREW DORSO |
| Final | 8/5/2024 | OK to Issue CofO | ANDREW DORSO |
| Smoke Detectors | 8/5/2024 | Approved | ANDREW DORSO |