15721 W STARE ST 91343
Certificate Information: 15721 W STARE ST 91343
- Application / Permit
- 22016-20000-23285
- Plan Check / Job No.
- B22VN11939
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED 2-CAR GARAGE (360 SF) AND REC ROOM (475 SF) INTO ADU PER CA GC 65852.2(e)(1)(A). ALL CONSTRUCTION PER WFPP.
- Permit Issued
- Issued on 8/24/2022
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2022 | VIVIAN LAO |
| Corrections Issued | 8/12/2022 | VIVIAN LAO |
| Plan Check Approved | 8/21/2022 | JOE VO |
| Issued | 8/24/2022 | APPLICANT |
| CofO in Progress | 12/1/2022 | JAVIER RAMOS JR |
| CofO Issued | 12/17/2022 | MICHAEL SMITH |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/17/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 8/17/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 9/9/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/16/2022 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 9/16/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| MERV13>=Rough | 9/16/2022 | Approved | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 9/16/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 9/22/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 9/22/2022 | Approved | ASHLEY THOMPSON |
| Shower Pan | 9/22/2022 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 9/26/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/26/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/9/2022 | Approved | JAVIER RAMOS JR |
| Final | 11/9/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 11/9/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| MERV13>=Final | 11/9/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/9/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 11/9/2022 | Approved | JAVIER RAMOS JR |
| Final | 11/17/2022 | Partial Approval | JAVIER RAMOS JR |
| Green Building Final | 11/17/2022 | Approved | JAVIER RAMOS JR |