19641-19645 W SYLVAN ST 91335
Certificate Information: 19641-19645 W SYLVAN ST 91335
- Application / Permit
- 22016-20000-23084
- Plan Check / Job No.
- B22VN11860
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 26' 9" X 11' 6" PORTION OF (E) SFD TO JUNIOR ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) AND 65852.22. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 9/8/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 8/4/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 8/5/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 8/11/2022 | APPLICANT |
| Applicant returned to address corrections | 8/26/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 9/8/2022 | ALEC MOUSAKHANIAN |
| Issued | 9/8/2022 | APPLICANT |
| CofO in Progress | 6/26/2023 | ALEXANDER HANDY |
| Permit Finaled | 7/17/2024 | JOHN JANSON |
| CofO Issued | 7/17/2024 | JOHN JANSON |
| Permit Finaled | 7/17/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/16/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/16/2022 | DAGOVERTO GUERRERO |
| ZI | Cleared | 8/16/2022 | BRENNEN OBETO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sayah,, Daniel H; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/21/2022 | Corrections Issued | STEVEN BACK |
| Deputy Drilled-In Anchors | 12/21/2022 | Conditional Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 12/23/2022 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Rough | 12/23/2022 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 12/23/2022 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 1/18/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Insulation | 1/18/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Interior/Exterior Lathing | 1/18/2023 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 1/18/2023 | Approved | ALEXANDER HANDY |
| Wood Frame | 1/18/2023 | Corrections Issued | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 2/1/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 2/1/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 2/1/2023 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 2/9/2023 | Approved | ALEXANDER HANDY |
| Insulation | 2/9/2023 | Approved | ALEXANDER HANDY |
| Special/Order Compliance | 3/13/2023 | Approved | ALEXANDER HANDY |
| Special/Order Compliance | 3/13/2023 | Partial Approval | SEAN WIRCH |
| Final | 6/23/2023 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 6/23/2023 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 6/23/2023 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 6/23/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Smoke Detectors | 6/23/2023 | Approved | ALEXANDER HANDY |