15336 W BLEDSOE ST 91342

Certificate Information: 15336 W BLEDSOE ST 91342

Application / Permit
22016-20000-23053
Plan Check / Job No.
B22VN11842
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Covert (e) 22’x26’ Detached Garage to ADU per CA Govt. Code 65852.2(e)(1)(A). Construction & Framing per WFPP
Permit Issued
Issued on 9/2/2022
Issuing Office
Current Status
CofO Issued on 12/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2022 APPLICANT
Assigned to Plan Check Engineer 8/8/2022 HANS SANTIAGO
Corrections Issued 8/8/2022 HANS SANTIAGO
Applicant returned to address corrections 8/25/2022 HANS SANTIAGO
Applicant returned to address corrections 8/26/2022 HANS SANTIAGO
Plan Check Approved 9/1/2022 ANDREW SANTIAGO
Issued 9/2/2022 APPLICANT
CofO in Progress 12/9/2022 ARAM AVEDISIAN
Permit Finaled 12/24/2022 MICHAEL SMITH
CofO Issued 12/24/2022 MICHAEL SMITH
Permit Finaled 12/24/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/9/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/10/2022 COLIN LOREDO
Sewer availability Cleared 8/11/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 8/30/2022 ANDREW SANTIAGO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/6/2022 No Result Entered KENNETH KUROWSKI
Footing/Foundation/Slab 9/8/2022 Corrections Issued CALEB MEISTER
PLUMBING-Rough 9/8/2022 Corrections Issued CALEB MEISTER
Footing/Foundation/Slab 9/15/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 9/15/2022 Partial Approval ARAM AVEDISIAN
Sewer 10/5/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 10/12/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 10/12/2022 Corrections Issued ARAM AVEDISIAN
Gas Test 10/12/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 10/12/2022 Corrections Issued ARAM AVEDISIAN
Underground Mechanical 10/12/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 10/17/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 10/17/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 10/17/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 10/17/2022 Approved ARAM AVEDISIAN
Insulation 10/20/2022 Corrections Issued THOMAS FINNILA
Drywall Nailing 10/24/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 11/3/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 12/1/2022 Approved CHRISTOPHER DELLEFIELD
Final 12/1/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 12/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 12/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 12/1/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 12/1/2022 Approved CHRISTOPHER DELLEFIELD
Final 12/6/2022 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 12/9/2022 Approved ARAM AVEDISIAN
Final 12/9/2022 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 12/9/2022 Approved ARAM AVEDISIAN
PLUMBING-Final 12/9/2022 Approved ARAM AVEDISIAN