13754-13756 N WHEELER AVE 91342
Certificate Information: 13754-13756 N WHEELER AVE 91342
- Application / Permit
- 22016-20000-22990
- Plan Check / Job No.
- B22VN11789
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: CONVERT (E) GARAGE IN SINGLE FAMILY DWELLING TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/4/2022
- Issuing Office
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/10/2022 | DANIEL YIP |
| Corrections Issued | 8/11/2022 | DANIEL YIP |
| Plan Check Approved | 9/1/2022 | DANIEL YIP |
| Issued | 9/4/2022 | APPLICANT |
| CofO in Progress | 7/25/2024 | KEVIN BERBERYAN |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
| CofO Issued | 8/7/2024 | RUBEN SALAS |
| Permit Finaled | 8/7/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/12/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/12/2022 | ROMAN GUTIERREZ |
| Miscellaneous | Cleared | 8/18/2022 | DANIEL SCHNEIDEREIT |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/31/2023 | No Access for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 5/31/2023 | Partial Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 6/5/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 6/6/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 11/28/2023 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/28/2023 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 11/28/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 12/4/2023 | Approved | KEVIN BERBERYAN |
| Sewer | 12/4/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/15/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 12/15/2023 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 12/15/2023 | Corrections Issued | KEVIN BERBERYAN |
| Insulation | 12/22/2023 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 1/4/2024 | Conditional Approval | KEVIN BERBERYAN |
| Shower Pan | 1/4/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 1/26/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 1/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 1/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 1/30/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Shower Pan | 2/27/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 3/22/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 3/28/2024 | Approved | KEVIN BERBERYAN |
| Final | 6/26/2024 | Corrections Issued | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/26/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 6/26/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 7/16/2024 | Partial Approval | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 7/16/2024 | Approved | KEVIN BERBERYAN |
| Final | 7/23/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| Service/Power Release | 7/23/2024 | Approved | KEVIN BERBERYAN |