11130 N BALBOA BLVD unit A 91344
Certificate Information: 11130 N BALBOA BLVD unit A 91344
- Application / Permit
- 22016-20000-22940
- Plan Check / Job No.
- B22VN11773
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Grocery Store
- Work Description
- ePlan *** PROPOSED TENANT IMPROVEMENT AND CHANGE OF USE FROM RETAIL TO SUPERMARKET WITH TAKE-OUT RESTAURANTS AND BAKERY; NO SEATING OR DINING ALLOWED
- Permit Issued
- Issued on 2/9/2023
- Issuing Office
- Current Status
- CofO Issued on 2/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | SINA KHOSRAVI |
| Corrections Issued | 8/30/2022 | SINA KHOSRAVI |
| Quality Review Completed | 9/7/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 11/17/2022 | SINA KHOSRAVI |
| Applicant returned to address corrections | 12/6/2022 | SINA KHOSRAVI |
| Applicant returned to address corrections | 12/15/2022 | SINA KHOSRAVI |
| Applicant returned to address corrections | 1/6/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 1/27/2023 | SINA KHOSRAVI |
| Plan Check Approved | 2/3/2023 | SINA KHOSRAVI |
| Issued | 2/9/2023 | APPLICANT |
| TCO Issued (Expire Date: 01-23-2024) | 7/27/2023 | JEFFREY DURAN |
| TCO Issued (Expire Date: 07-09-2024) | 1/11/2024 | JEFFREY DURAN |
| CofO in Progress | 1/31/2024 | DEANDRE HOFFMAN |
| Permit Finaled | 2/2/2024 | JEFFREY DURAN |
| CofO Issued | 2/2/2024 | JEFFREY DURAN |
| Permit Finaled | 2/2/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 12/5/2022 | COLIN LOREDO |
| ZA Case | Cleared | 12/8/2022 | JASON CHAN |
| ZA Case | Cleared | 12/8/2022 | JASON CHAN |
| ZA Case | Cleared | 12/8/2022 | JASON CHAN |
| ZA Case | Cleared | 12/8/2022 | JASON CHAN |
| ZA Case | Cleared | 12/12/2022 | ANGELA WILLIAMS |
| ZA Case | Cleared | 12/12/2022 | ANGELA WILLIAMS |
| Specific Plan | Cleared | 12/27/2022 | CLAUDIA RODRIGUEZ |
| Fire Marshal Fire Life Safety | Cleared | 1/13/2023 | ANDREW KO |
| DAS Clearance | Cleared | 1/17/2023 | Hernan Arreola |
| Food Service Establishment | Cleared | 1/17/2023 | KENNETH BROWNE |
| Food establishment approval | Cleared | 1/18/2023 | LACDHS APPROVED |
| Grading Pre-Inspection | Cleared | 1/18/2023 | TEODORO DIAZ RODRIGUEZ |
| Green Code | Cleared | 1/26/2023 | AARON COSTA |
Contact Information
| Contractor | Distinctive Contractors Corporation; Lic. No.: 1026213-B | , |
| Engineer | Monzon,, Eric Vibar; Lic. No.: C91728 | 9263 SANTENAY WAY SACRAMENTO, CA 95829 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/3/2023 | Corrections Issued | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 3/3/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 3/6/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 3/7/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 3/16/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 3/24/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 3/30/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 3/30/2023 | Partial Inspection | DEANDRE HOFFMAN |
| T-Bar Ceiling | 6/9/2023 | Partial Inspection | DEANDRE HOFFMAN |
| T-Bar Ceiling | 6/26/2023 | Partial Inspection | DEANDRE HOFFMAN |
| T-Bar Ceiling | 6/30/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Pre-Inspection | 7/11/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Pre-Inspection | 7/25/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Special/Order Compliance | 1/3/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 1/26/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Green Building Final | 1/26/2024 | Approved | DEANDRE HOFFMAN |
| Green Building Rough | 1/26/2024 | Approved | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 1/26/2024 | Approved | DEANDRE HOFFMAN |
| Wood Frame | 1/26/2024 | Approved | DEANDRE HOFFMAN |
| Final | 1/31/2024 | OK to Issue CofO | DEANDRE HOFFMAN |