19643-19645 W SYLVAN ST 91335
Certificate Information: 19643-19645 W SYLVAN ST 91335
- Application / Permit
- 22016-20000-22846
- Plan Check / Job No.
- B22VN11746
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E)ATT. GARAGE (400 S.F) ALONG WITH (70 S.F) OF (E) LAUNDRY ROOM TO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 8/26/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | SARKIS HARABEDIAN |
| Corrections Issued | 8/4/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 8/11/2022 | APPLICANT |
| Plan Check Approved | 8/26/2022 | YAQUB MIRZA |
| Issued | 8/26/2022 | APPLICANT |
| CofO in Progress | 9/28/2023 | ALEXANDER HANDY |
| Permit Finaled | 11/14/2023 | JOHN JANSON |
| CofO Issued | 11/14/2023 | JOHN JANSON |
| Permit Finaled | 11/14/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/12/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/12/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sayah,, Daniel H; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/21/2022 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 11/21/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 11/21/2022 | Partial Approval | STEVEN BACK |
| Deputy Drilled-In Anchors | 1/27/2023 | Conditional Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 2/1/2023 | Partial Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 3/8/2023 | Approved | ALEXANDER HANDY |
| Rough-Elec/Plmb/HVAC | 3/8/2023 | Corrections Issued | ALEXANDER HANDY |
| Wood Frame | 3/8/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Interior/Exterior Lathing | 3/17/2023 | Partial Approval | ALEXANDER HANDY |
| Insulation | 4/4/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| Insulation | 4/11/2023 | Corrections Issued | JEFFREY BULL |
| ELECTRICAL-Rough | 4/21/2023 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 4/21/2023 | Approved | ALEXANDER HANDY |
| Insulation | 4/21/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 4/21/2023 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 5/9/2023 | Approved | ALEXANDER HANDY |
| Wood Frame | 5/9/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 9/21/2023 | Approved | ALEXANDER HANDY |
| Final | 9/21/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 9/21/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 9/21/2023 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 9/21/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 9/27/2023 | Approved | ALEXANDER HANDY |
| Final | 9/27/2023 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 9/27/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 9/27/2023 | Approved | ALEXANDER HANDY |