5975 N SADRING AVE 91367
Certificate Information: 5975 N SADRING AVE 91367
- Application / Permit
- 22016-20000-22832
- Plan Check / Job No.
- B22VN11735
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX. ACCESSORY LIVING QUARTERS/WORKSHOP/GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). WORK DONE PER WFPP.
- Permit Issued
- Issued on 1/11/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 8/4/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 8/8/2022 | APPLICANT |
| Applicant returned to address corrections | 12/30/2022 | ISIS ARGUETA |
| Plan Check Approved | 1/11/2023 | ROSENDO MEDINA |
| Issued | 1/11/2023 | APPLICANT |
| CofO in Progress | 9/2/2025 | TROY SANDERS |
| Permit Finaled | 9/24/2025 | JOHN JANSON |
| CofO Issued | 9/24/2025 | JOHN JANSON |
| Permit Finaled | 9/24/2025 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 12/15/2022 | NELSON RODRIGUEZ |
| Address approval | Cleared | 12/16/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 1/3/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/23/2023 | No Access for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 1/23/2023 | No Access for Inspection | TROY SANDERS |
| Green Building Rough | 1/23/2023 | No Access for Inspection | TROY SANDERS |
| HVAC-Rough | 1/23/2023 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 1/23/2023 | No Access for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 1/25/2023 | Approved | TROY SANDERS |
| HVAC-Rough | 1/25/2023 | Approved | TROY SANDERS |
| PLUMBING-Rough | 1/25/2023 | Approved | TROY SANDERS |
| Insulation | 3/29/2023 | Approved | TROY SANDERS |
| Pre-Inspection | 3/29/2023 | Partial Inspection | JUSTIN HAWLEY |
| Drywall Nailing | 4/11/2023 | Approved | HORACE FULTZ |
| Shower Pan | 4/11/2023 | Partial Inspection | HORACE FULTZ |
| Interior/Exterior Lathing | 4/13/2023 | Partial Approval | TROY SANDERS |
| Shower Pan | 4/13/2023 | Approved | TROY SANDERS |
| Special/Order Compliance | 2/9/2024 | Approved | GEVORK IPCHYAN |
| Underground Mechanical | 2/9/2024 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 2/3/2025 | Approved | TROY SANDERS |
| Green Building Rough | 2/3/2025 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Not Ready | TROY SANDERS |
| BUILDING-Rough-Frame | 2/6/2025 | Approved | TROY SANDERS |
| Final | 2/6/2025 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 2/6/2025 | Not Ready for Inspection | TROY SANDERS |
| Green Building Rough | 2/6/2025 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/6/2025 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 2/6/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 3/25/2025 | Approved | TROY SANDERS |
| HVAC-Final | 3/25/2025 | Approved | TROY SANDERS |
| PLUMBING-Final | 3/25/2025 | Approved | TROY SANDERS |
| Final | 8/28/2025 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 8/28/2025 | Approved | TROY SANDERS |