10568 W OHIO AVE 90024
Certificate Information: 10568 W OHIO AVE 90024
- Application / Permit
- 22016-20000-22720
- Plan Check / Job No.
- B22VN11681
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 23'-6" x 38'-0" SECOND FLOOR DETACHED REC ROOM INTO A (N) ACCESSORY DWELLING UNIT PER LAMC A.33(c) AND (d).
- Permit Issued
- Issued on 10/5/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2022 | ALFRED RAMIREZ |
| Corrections Issued | 7/29/2022 | ALFRED RAMIREZ |
| Plan Check Approved | 10/5/2022 | OMAR GARNICA |
| Issued | 10/5/2022 | APPLICANT |
| CofO in Progress | 6/6/2023 | JESUS PINEDA |
| Permit Finaled | 6/7/2023 | DANIEL ORRANTE |
| CofO Issued | 6/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 8/27/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2022 | JOSE HERNANDEZ |
| Construction near power lines | Cleared | 9/23/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/25/2022 | Corrections Issued | STEPHANIE SWANSON |
| Final | 4/3/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 4/3/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Green Building Rough | 4/3/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| METHANE-Final | 4/3/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| METHANE-Rough | 4/3/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 4/3/2023 | SGSOV Not Ready | CLAYTON GRAHAM |
| Smoke Detectors | 4/3/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Wood Frame | 4/3/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Final | 4/17/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 4/17/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Green Building Rough | 4/17/2023 | Approved | CLAYTON GRAHAM |
| METHANE-Final | 4/17/2023 | Approved | CLAYTON GRAHAM |
| METHANE-Rough | 4/17/2023 | Approved | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 4/17/2023 | SGSOV Approved | CLAYTON GRAHAM |
| Smoke Detectors | 4/17/2023 | Approved | CLAYTON GRAHAM |
| Wood Frame | 4/17/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Final | 4/27/2023 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 4/27/2023 | Approved | JESUS PINEDA |
| Wood Frame | 4/27/2023 | Approved | JESUS PINEDA |
| Final | 6/5/2023 | OK to Issue CofO | JESUS PINEDA |