10062 N WEALTHA AVE 91352
Certificate Information: 10062 N WEALTHA AVE 91352
- Application / Permit
- 22016-20000-22604
- Plan Check / Job No.
- B22VN11593
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN* CONVERT EXISTING 12' X 30' DETACHED STOREHOUSE BUILDING TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) - ALL WORK PER WFPP.
- Permit Issued
- Issued on 3/28/2023
- Issuing Office
- Current Status
- CofO Issued on 12/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2022 | ALEC MOUSAKHANIAN |
| Corrections Issued | 8/13/2022 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 10/12/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 2/24/2023 | MADISON ODELL |
| Plan Check Approved | 3/17/2023 | MADISON ODELL |
| Issued | 3/28/2023 | APPLICANT |
| CofO in Progress | 11/30/2023 | MATTHEW NELSON |
| CofO Issued | 12/19/2023 | RUBEN SALAS |
| Permit Finaled | 12/19/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/12/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 9/12/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/12/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2022 | CARLOS AGUILERA |
| HPOZ | Cleared | 9/26/2022 | SUKI GERSHENHORN |
| Grading Pre-Inspection | Cleared | 1/3/2023 | KIRK LINKLATER |
| Specific Plan | Cleared | 1/5/2023 | CECILIA CASTILLO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/21/2023 | Partial Approval | DAVID ANDERSON |
| Sewer | 6/21/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/25/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 7/25/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 7/25/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 8/9/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/9/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 8/9/2023 | Approved | DAVID ANDERSON |
| Insulation | 8/16/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/16/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 8/16/2023 | Corrections Issued | DAVID ANDERSON |
| Drywall Nailing | 8/31/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 8/31/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Shower Pan | 9/14/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/3/2023 | Approved | WILLIAM WREN |
| Final | 11/20/2023 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 11/20/2023 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 11/20/2023 | Approved | DAVID ANDERSON |
| Final | 11/29/2023 | OK to Issue CofO | MATTHEW NELSON |