12965 W ROMONT ST 91342
Certificate Information: 12965 W ROMONT ST 91342
- Application / Permit
- 22016-20000-22591
- Plan Check / Job No.
- B22VN11585
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (110 SF) PORTION OF AND ENCLOSE 10'-0" X 24'-5" (243 SF) PORTION OF EXISTING PATIO COVER AND INTERIOR REMODEL TO THE (E) SINGLE-FAMILY DWELLING. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 11/7/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 7/28/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 10/7/2022 | JESSE ARELLANO |
| Plan Check Approved | 11/7/2023 | ISIS ARGUETA |
| Issued | 11/7/2023 | APPLICANT |
| CofO in Progress | 7/17/2024 | ROBERT GOLD |
| Permit Finaled | 7/19/2024 | RUBEN SALAS |
| CofO Issued | 7/19/2024 | RUBEN SALAS |
| Permit Finaled | 7/19/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/9/2023 | DANIEL ABRAMYAN |
| Roof/Waste drainage to street | Cleared | 10/11/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/29/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 3/22/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 3/22/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 3/27/2024 | Partial Approval | KEVIN BERBERYAN |
| PLUMBING-Rough | 3/27/2024 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 3/27/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 4/5/2024 | Partial Approval | KEVIN BERBERYAN |
| Green Building Rough | 4/5/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 4/5/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/5/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 4/9/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 4/9/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 4/12/2024 | Approved | KEVIN BERBERYAN |
| Final | 6/12/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 6/12/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 6/12/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 6/28/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 6/28/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/28/2024 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 6/28/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 7/1/2024 | Approved | KEVIN BERBERYAN |