13630 N LINFIELD AVE 91342

Certificate Information: 13630 N LINFIELD AVE 91342

Application / Permit
22016-20000-22461
Plan Check / Job No.
B22VN11529
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 11/8/2022
Issuing Office
Current Status
CofO Issued on 12/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 DANIEL YIP
Corrections Issued 8/12/2022 DANIEL YIP
Applicant returned to address corrections 10/7/2022 DANIEL YIP
Plan Check Approved 10/14/2022 DANIEL YIP
Issued 11/8/2022 APPLICANT
CofO in Progress 12/16/2023 ROBERT GOLD
CofO Issued 12/21/2023 RUBEN SALAS
Permit Finaled 12/21/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/31/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/31/2022 COLIN LOREDO
Sewer availability Cleared 8/31/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 9/6/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/14/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 4/14/2023 Partial Approval ARAM AVEDISIAN
Sewer 4/14/2023 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 4/24/2023 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 4/24/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 4/24/2023 Approved ARAM AVEDISIAN
Sewer 4/24/2023 Approved ARAM AVEDISIAN
Insulation 5/15/2023 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 5/24/2023 Approved ARAM AVEDISIAN
Insulation 5/24/2023 Approved ARAM AVEDISIAN
Drywall Nailing 6/2/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 6/12/2023 Approved MICHEL ABAJAN
Shower Pan 6/12/2023 Approved MICHEL ABAJAN
Gas Test 7/12/2023 Corrections Issued RAUL OLAGI
Final 7/24/2023 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/24/2023 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 7/24/2023 Corrections Issued MISAEL ESPARZA
Final 8/21/2023 Corrections Issued DAVID ANDERSON
Smoke Detectors 8/21/2023 Approved DAVID ANDERSON
Final 9/20/2023 Corrections Issued KEVIN BERBERYAN
Final 9/26/2023 OK to Issue CofO KEVIN BERBERYAN
Final 10/3/2023 Corrections Issued KEVIN BERBERYAN