8533 N COLUMBUS AVE 91343
Certificate Information: 8533 N COLUMBUS AVE 91343
- Application / Permit
- 22016-20000-22445
- Plan Check / Job No.
- B22VN11524
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment House
- Work Description
- (eplan) REMOVE EXISTING ONE PARKING SPACE AND CONVERT IT TO LAUNDRY ROOM
- Permit Issued
- Issued on 12/21/2023
- Issuing Office
- Current Status
- CofO Issued on 11/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2022 | YOUNG KIM |
| Corrections Issued | 8/16/2022 | YOUNG KIM |
| Quality Review Completed | 8/19/2022 | GARO TELMI |
| Applicant returned to address corrections | 10/6/2022 | YOUNG KIM |
| Plan Check Approved | 10/25/2022 | YOUNG KIM |
| Issued | 12/21/2023 | APPLICANT |
| CofO in Progress | 10/29/2024 | ANDREW DORSO |
| Permit Finaled | 11/1/2024 | JEFFREY DURAN |
| CofO Issued | 11/1/2024 | JEFFREY DURAN |
| Permit Finaled | 11/1/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/1/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 9/2/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 9/2/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 9/2/2022 | MEGAN GODINEZ |
| "Q" conditions | Cleared | 9/6/2022 | ASHLEY RODARTE |
| DAS Clearance | Cleared | 9/12/2022 | YOUNG KIM |
| Tenant Habitability Plan | Cleared | 9/20/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | C W General Construction Inc; Lic. No.: 971704-B | , |
| Engineer | Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 | 1171 JUSTIN AVE APT 3 GLENDALE, CA 91201 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/27/2023 | No Access for Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 12/28/2023 | Corrections Issued | ANDREW DORSO |
| Footing/Foundation/Slab | 1/5/2024 | Not Ready for Inspection | ANDREW DORSO |
| Masonry Wall/Backfill | 1/24/2024 | Not Ready for Inspection | ANDREW DORSO |
| Pre-Inspection | 1/24/2024 | Not Ready for Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 2/8/2024 | Approved | ANDREW DORSO |
| Special/Order Compliance | 2/8/2024 | Partial Inspection | MELVIN GIRTON |
| Wood Frame | 2/27/2024 | Not Ready for Inspection | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Not Ready for Inspection | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 4/11/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 4/16/2024 | Partial Inspection | ANDREW DORSO |
| Interior/Exterior Lathing | 4/18/2024 | Approved | ANDREW DORSO |
| Wood Frame | 6/3/2024 | Corrections Issued | ANDREW DORSO |
| Wood Frame | 8/27/2024 | Not Ready for Inspection | ANDREW DORSO |
| Insulation | 9/10/2024 | Approved | KENNETH ROBERTS |
| Drywall Nailing | 9/16/2024 | Corrections Issued | DANNY RODRIGUEZ |
| Interior/Exterior Lathing | 9/16/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 9/24/2024 | Approved | ANDREW DORSO |
| Final | 10/7/2024 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 10/7/2024 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 10/7/2024 | Approved | ANDREW DORSO |
| Final | 10/10/2024 | Not Ready for Inspection | ANDREW DORSO |
| Final | 10/15/2024 | OK to Issue CofO | ANDREW DORSO |