20544 W VENTURA BLVD 91364
Certificate Information: 20544 W VENTURA BLVD 91364
- Application / Permit
- 22016-20000-22444
- Plan Check / Job No.
- B22VN11523
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- REMODEL (E) LEASING OFFICE AND REC. CENTER AREA
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Current Status
- Permit Finaled on 5/3/2023
Permit Application Status History
| Submitted | 8/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | SEAN SHAHMIRI |
| Corrections Issued | 8/29/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 9/2/2022 | OMID HEDAYAT |
| Applicant returned to address corrections | 9/16/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 1/23/2023 | SEAN SHAHMIRI |
| Issued | 1/23/2023 | APPLICANT |
| Permit Finaled | 5/3/2023 | BRIAN KELLY |
Permit Application Clearance Information
| "D" conditions | Cleared | 11/7/2022 | MAXFIELD VERMY |
| "Q" conditions | Cleared | 11/7/2022 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 11/7/2022 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 11/7/2022 | MAXFIELD VERMY |
| ZA Case | Cleared | 11/7/2022 | MAXFIELD VERMY |
| ZA Case | Cleared | 11/7/2022 | MAXFIELD VERMY |
| ZA Case | Cleared | 11/7/2022 | MAXFIELD VERMY |
| ZA Case | Cleared | 11/7/2022 | MAXFIELD VERMY |
| ZI | Cleared | 11/7/2022 | MAXFIELD VERMY |
| Green Code | Cleared | 11/28/2022 | Hernan Arreola |
| Specific Plan | Cleared | 12/15/2022 | ERIN NASH |
| DAS Clearance | Cleared | 12/21/2022 | Hernan Arreola |
| Fire Marshal Fire Life Safety | Cleared | 1/4/2023 | WILLIAM JOHNS |
Contact Information
| Contractor | Rovner Mike Construction Inc; Lic. No.: 795729-C33 | 5400 TECH CIR MOORPARK, CA 93021 |
| Landscape Architect | Marczynski,, Frank R; Lic. No.: LA2196 | 2030 GALVESTON STREET SAN DIEGO, CA 92110 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 1/26/2023 | Partial Approval | BRIAN KELLY |
| Drywall Nailing | 1/31/2023 | Approved | BRIAN KELLY |
| Footing/Foundation/Slab | 3/3/2023 | Partial Approval | BRIAN KELLY |
| Excavation/Setback/Form/Re-Bar | 3/6/2023 | Not Ready for Inspection | BRIAN KELLY |
| Footing/Foundation/Slab | 3/6/2023 | Not Ready for Inspection | BRIAN KELLY |
| Excavation/Setback/Form/Re-Bar | 3/9/2023 | Partial Approval | BRIAN KELLY |
| Light Gage Steel Frame | 3/17/2023 | Not Ready for Inspection | BRIAN KELLY |
| Masonry Wall/Backfill | 3/17/2023 | Approved | BRIAN KELLY |
| T-Bar Ceiling | 3/30/2023 | Not Ready for Inspection | BRIAN KELLY |
| Final | 4/21/2023 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 4/21/2023 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 4/21/2023 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 4/21/2023 | Not Ready for Inspection | BRIAN KELLY |
| Final | 5/3/2023 | Permit Finaled | BRIAN KELLY |
| Green Building Final | 5/3/2023 | Approved | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 5/3/2023 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 5/3/2023 | Approved | BRIAN KELLY |