6218 N LANKERSHIM BLVD 91606

Certificate Information: 6218 N LANKERSHIM BLVD 91606

Application / Permit
22016-20000-22401
Plan Check / Job No.
B22VN11509
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
ePlan Change of use to retail and office area ; work to include removing (3) existing roll-up door with new storfront and parking area re-striping
Permit Issued
Issued on 3/15/2023
Issuing Office
Current Status
CofO Issued on 2/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2022 APPLICANT
Assigned to Plan Check Engineer 10/20/2022 SINA KHOSRAVI
Corrections Issued 10/28/2022 SINA KHOSRAVI
Quality Review Completed 11/4/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 11/10/2022 SINA KHOSRAVI
Applicant returned to address corrections 12/6/2022 SINA KHOSRAVI
Applicant returned to address corrections 12/19/2022 SINA KHOSRAVI
Applicant returned to address corrections 2/21/2023 SINA KHOSRAVI
Plan Check Approved 2/22/2023 SINA KHOSRAVI
Issued 3/15/2023 SHANNON HAAS
CofO in Progress 2/13/2024 ROBERT DAVIS
Permit Finaled 2/15/2024 JEFFREY DURAN
CofO Issued 2/15/2024 JEFFREY DURAN
Permit Finaled 2/15/2024 JEFFREY DURAN

Permit Application Clearance Information

"Q" conditions Cleared 12/7/2022 MIGUEL GAMBOA
Sewer availability Cleared 12/7/2022 CARLOS AGUILERA
ZA Case Cleared 12/7/2022 MIGUEL GAMBOA
ZA Case Cleared 12/7/2022 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 12/8/2022 CARLOS AGUILERA
Green Code Cleared 12/28/2022 MICHAEL AYERS
DAS Clearance Cleared 1/30/2023 Hernan Arreola

Contact Information

Architect Dwyer,, Mark Steven; Lic. No.: NA23283       ,
Contractor B N C Industries Inc; Lic. No.: 1024294-B       ,
Engineer Rosepink,, Dustin; Lic. No.: S5885 24255 VIA MADRUGADA      MISSION VIEJO, CA 92692

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/28/2023 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/31/2023 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 4/3/2023 Conditional Approval ROBERT DAVIS
Masonry Wall/Backfill 4/4/2023 Partial Approval ROBERT DAVIS
Masonry Wall/Backfill 4/10/2023 Partial Approval DANIEL VARNUM
Reinforced Masonry Frame 4/10/2023 Partial Approval DANIEL VARNUM
Drywall Nailing 5/12/2023 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 5/12/2023 Approved ROBERT DAVIS
Insulation 5/12/2023 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 5/12/2023 Not Ready for Inspection ROBERT DAVIS
Masonry Wall/Backfill 5/12/2023 Approved ROBERT DAVIS
Wood Frame 5/12/2023 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 5/16/2023 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 5/16/2023 Partial Approval ROBERT DAVIS
Wall Anchors 5/16/2023 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 5/23/2023 Partial Approval ROBERT DAVIS
Wood Frame 5/23/2023 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 5/26/2023 Not Ready for Inspection ROBERT DAVIS
Light Gage Steel Frame 5/26/2023 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 6/5/2023 Partial Approval ROBERT DAVIS
T-Bar Ceiling 7/6/2023 Approved ROBERT DAVIS
Special/Order Compliance 9/15/2023 Approved ROBERT DAVIS
Final 11/9/2023 Not Ready for Inspection ROBERT DAVIS
Green Building Final 11/9/2023 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 11/9/2023 SGSOV Not Ready ROBERT DAVIS
Smoke Detectors 11/9/2023 Approved ROBERT DAVIS
Wood Frame 11/9/2023 Approved ROBERT DAVIS
Final 11/20/2023 Not Ready for Inspection ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV No Gas ROBERT DAVIS
Special/Order Compliance 11/20/2023 Approved ROBERT DAVIS
Final 12/1/2023 Not Ready for Inspection ROBERT DAVIS
Special/Order Compliance 12/1/2023 Partial Inspection ROBERT DAVIS
Final 2/6/2024 OK to Issue CofO ROBERT DAVIS
Special/Order Compliance 2/6/2024 Partial Inspection ROBERT DAVIS
Final 2/9/2024 Not Ready for Inspection ROBERT DAVIS